6. CHECKS AFTER COMMISSIONING
6.1. Condensate removal
Check that the removal of condensate is not obstructed, on both the boiler side
and the pipe side.
6.2. Gas supply
Check that the gas pipe diameter is correctly sized:
It is necessary to stop all the boilers together abruptly using the boiler room
main circuit breaker to check that the gas pressure regulator safety device is
not triggered.
If this is triggered, the gas pipe is undersized. After this operation, reengage the
circuit breaker. The boilers must start automatically, if not, consult the supplier
of the gas pressure regulator.
Summary of Contents for STRATTON MK3 Series
Page 2: ......
Page 13: ...06 02 2023 13 154 STRATTON MK3 Installation Use and Maintenance...
Page 44: ...44 154 STRATTON MK3 Installation Use and Maintenance 00U07428680 C Figure 19 Wiring diagram...
Page 45: ...06 02 2023 45 154 STRATTON MK3 Installation Use and Maintenance...
Page 149: ...06 02 2023 149 154 STRATTON MK3 Installation Use and Maintenance...
Page 150: ...150 154 STRATTON MK3 Installation Use and Maintenance 00U07428680 C...
Page 151: ...06 02 2023 151 154 STRATTON MK3 Installation Use and Maintenance...
Page 152: ...152 154 STRATTON MK3 Installation Use and Maintenance 00U07428680 C...
Page 153: ...06 02 2023 153 154 STRATTON MK3 Installation Use and Maintenance...