Test Step
Measurements/Test Results
Seq.
No.
Description
Required/No
minal (incl.
tolerance)
Measured/
Calculated
Remarks/Calculations
Pass/
No
pass
66.
FOR THE GAITWAY-3D 170/65 and 190/65:
Route both left load cell cables to the amplifier through the motor
compartment:
1) one tie-wrap in the tie-mount next to the front left load cell.
2) one tie-wrap in the tie-mount under the motor compartment
3) one tie-wrap on the existing cables on the plate under the motor.
4) one tie-wrap on the existing cables at left side of the motor.
5) one tie-wrap on the existing cables in front of the motor cover.
6) one tie-wrap on the existing cables close to center hole of front panel.
Let the tie wraps loose.
6x Tie-wrap