GM · CONVERTING UNIT
65
27.
Installation guide
To secure that the installation and training can be carried out without problems and waste of time due to
missing materials or on site preparations for the installation it is very important that the following
preparations and items are ready before the arrival of the machine:
Unloading the machine:
- A fork lift with min. 1000 kg lifting capacity must be ready to get the craters down from the truck.
- A pallet jack is needed to move and align the machines.
Electric Power:
Power for the machines must be prepared.
-
DCOAT and BUFFER
3W+N+PE 400V AC 50hz 32A
-
COOLING UNIT
3W+N+PE 400V AC 50hz 16A
Air supply:
Min. 6 bar and 20L/min is needed, tube Ø8mm
Cooling Unit (water cooled lamp)
The cooling unit has to be placed at the same level (if possible).
Add Texaco Havoline XLI 7.5% volume to the cooling water. If the Cooling unit is in freezing
surroundings, use XLC 33% volume down tot -20 degree Celsius.
Cooling fan (air cooled lamp)
All new GM converting units delivered with air cooled lamps, are ozonfree.
This means there are no needs for ozonfilter. The lifespan for the bulp is aprox.1000hrs.
If the GM converting unit is an older configuration, external fan must be connected to a OZON filter or
an external exhaust. Use the delivered ozonfilter from us.
Verify that the fan is operating in the correct direction and the gate is working correctly (opens up when
hot, closes when cold). If external exhaust is used the capacity must på 390 m3/h and suction pressure
910 Pascal at full power and 160 at standby. There must be no more than 2 meters between the fan and
the UV lamp. The tube must not make any sharp turns. Tube diameter is 100mm.