Positioner Action Change (4700P/4800P Only)
Whenever it becomes necessary to change positioner action from direct to reverse or vice versa,
it is important to be familiar with the following steps.
To remove or install the cam safely, the valve position must correspond to the low signal line on
lobe.
The positioner supply line, the vent and the lever S/A must be reversed.
From Air to Open / Direct to Air to Open/Reverse
1. Perform Steps 1 and 2 from “Cam Lobe Change” on page 49 for
Air to Open/Direct
Acting Positioner
. Cam is now removed.
2. Proceed to
Field Mounting and Calibration
section for
Air to Open/Reverse Acting
Positioner
and proceed as stated.
From Air to Open / Reverse to Air to Open/Direct
1. Perform Steps 1, 2 and 3 from “Cam Lobe Change” on page 49 for
Air to Open/
Reverse Positioner
. Cam is now removed.
2. Slowly reduce pressure applied to actuator to zero. (If handwheel was used to
place valve in open position back it off completely.) Valve is now closed. Remove
independent regulated air line from actuator.
3. Proceed to
Field Mounting and Calibration
section for
Air to Open/Direct Acting
Positioner
and proceed as stated.
From Air to Close / Direct to Air to Close/Reverse
1. Perform Steps 1 and 2 from “Cam Lobe Change” on page 49 for
Air to Close/Direct
Acting Positioner
. Cam is now removed.
2. Proceed to
Field Mounting and Calibration
section for
Air to Close/Reverse Acting
Positioner
and proceed as stated.
From Air to Close / Reverse to Air to Close/Direct
1. Perform Steps 1, 2 and 3 from “Cam Lobe Change” on page 49 for
Air to Close/
Reverse Acting Positioner
. Cam is now removed.
2. Slowly reduce pressure applied to actuator to zero. (If handwheel was used to
place valve in closed position back it off completely.) Valve is now open. Remove
independent regulated air line from actuator.
3. Proceed to
Field Mounting and Calibration
section for
Air to Close/Direct Acting
Positioner
and proceed as stated.
Summary of Contents for Masoneilan 4700E
Page 4: ...This page intentionally left blank ...
Page 8: ...This page intentionally left blank ...
Page 10: ...This page intentionally left blank ...
Page 14: ...This page intentionally left blank ...
Page 18: ...This page intentionally left blank ...
Page 40: ... 2015 General Electric Company All rights reserved 40 GE Oil Gas Figure 13 FM Installation ...
Page 42: ... 2015 General Electric Company All rights reserved 42 GE Oil Gas Figure 15 ATEX Installation ...
Page 46: ...This page intentionally left blank ...
Page 66: ... 2015 General Electric Company All rights reserved 66 GE Oil Gas ...
Page 78: ...This page intentionally left blank ...
Page 79: ......