Performance test run order
Under certain conditions, some performance tests should be run in a specific order ac-
cording to the table below. In other circumstances (for example, when membranes are
changed on a specific valve), tests may be run independently of each other.
Test order
Condition
Run valve module tests in the following order:
System leakage test fails
•
Inlet valve
•
Outlet valve
•
Column valve
•
Air trap valve
•
Mixer valve
Ensure that Air Trap valve and Column valve tests
are passed. The Air Trap leakage test will fail if
either of these tests fails, even if the Air Trap itself
does not leak.
Before running Air Trap leakage
test