13-8-639 Page 18
Cold Weather
(Down To +10
o
F)
1. Be sure all drains, traps, and control lines, including pressure transducer lines are heated to avoid
freezing of condensate. Heat tape with thermostat control is generally satisfactory for this purpose
and can be obtained at various local plumbing or hardware outlets at nominal cost.
2. Provisions to bypass the aftercooler must be made. Since cold air contains very little moisture,
successful operation can be achieved without the aftercooler.
3. Provide at least some simple shelter such as a plywood windbreak to protect against drifting snow.
4. Use only Gardner Denver AEON 9000SP lubricant.
5. Monitor unit carefully during start-up and operation to be sure it is functioning normally.
Remember unsheltered (outside) installations should be avoided where possible. Installation next to a
heated building where enough heat can be used to keep the compressor room above freezing will save
many complications in the operation and installation of the unit.
AUXILIARY AIR RECEIVER
- An auxiliary air receiver is not required if the piping system is large and
provides sufficient storage capacity to prevent rapid cycling. When used, an air receiver should be of
adequate size, provided with a relief valve of proper setting, a pressure gauge and a means of draining
condensate
STANDARD MOISTURE
SEPARATOR/TRAP
- The unit is equipped with a built-in aftercooler, a
combination moisture separator and trap piped into the system down stream of the aftercooler.
CONTROL PIPING
- Control piping is not necessary since the rotary screw unit is factory wired and piped
for the control system specified.
INLET LINE
- Where an inlet line is used between the air filter and the compressor, it must be thoroughly
cleaned on the inside to prevent dirt or scale from entering the compressor.
If welded construction is
used, the line must be shot blasted and cleaned to remove welding scale
. In either case, the inlet
line must be coated internally by galvanizing or painting with a moisture and oil-proof sealing lacquer. Up
to ten (10) feet in length, the inlet line should be the full size of the inlet opening on the compressor. If an
extra-long line is necessary, the pipe size should be increased according to “Inlet Line Length Chart”,
page 18.
Accessibility for inlet air filter servicing must be considered when relocating the filters from the unit to a
remote location.
INLET LINE LENGTHS
Length of Inlet Line
Diameter of Pipe Size
0 to 10 Feet ............................................. Same as Compressor Inlet Opening
10 to 17 Feet ........................................... One Size Larger Than Inlet Opening
17 to 38 Feet ........................................... Two Sizes Larger Than Inlet Opening
DISCHARGE SERVICE LINE
- The discharge service line connection is made on the side of the
package, (See Outline Drawing 300EFA804). A hand operated valve, (air service valve) must be installed
between the unit and the customer’s air system. If a fast operating valve, such as a ball valve is used, it
must be closed slowly to give the intake valve time to shut and keep the discharge pressure from rising
too rapidly.
Summary of Contents for INTEGRA EFA99F
Page 15: ...13 8 639 Page 15 Figure 2 2 OUTLINE UNIT PACKAGE 300EFA804 A Ref Drawing ...
Page 39: ...13 8 639 Page 39 WIRING DIAGRAMS 3 PHASE ...
Page 40: ...13 8 639 Page 40 WIRING DIAGRAMS 3 PHASE ...
Page 41: ...13 8 639 Page 41 WIRING DIAGRAMS 3 PHASE ...
Page 42: ...13 8 639 Page 42 WIRING DIAGRAMS 1 PHASE ...
Page 43: ...13 8 639 Page 43 WIRING DIAGRAM 1 PHASE ...