7.3 Changing the Tape
The sensing tape is consumed during the measurement process and must be replaced on a
periodic basis. The amount of tape remaining is indicated on the
Analysis
tab of the GUI and
the GEN menu on the hand held controller. In addition, an alarm will be presented on the
Alarms
tab of the GUI and the hand held controller when the tape level is low.
To replace the tape:
a) Check the hand held display for any alarms.
b) Disable alarms by pressing the
BYPASS
button on the hand held controller
c) Turn off gas to the analyzer. Pull back the Compression Head and inspect the Sample
Chamber (Figure 7-1) for paper dust and dirt. If necessary, remove the Sample chamber
assembly and clean it.
Figure7-1: Sample Chamber Assembly
d) Remove the tape cover from the left side of the chassis to view the tape enclosure.
Figure 7-2 presents the open enclosure with various components identified. .
e) Remove the screw-on disks (not shown) from the supply reel (1) and take-up reel (2).
Summary of Contents for ProTech903
Page 2: ......
Page 96: ...Revision 14 96 August 02 2019 Figure 5 19 Event Log...
Page 122: ...Revision 14 122 August 02 2019 Figure 5 38 Typical Modicon with Floating Point List...
Page 124: ...Revision 14 124 August 02 2019 Figure 5 40 Expanded Modbus Nodes...
Page 175: ...Revision 14 175 August 02 2019 Figure 9 17 Non Isolated 4 20 mA Inputs...
Page 190: ...Revision 14 190 August 02 2019...