Fusion Installation & Commissioning Manual Approved document No UI-FBU-01 issue 3.0
15
INSTALLATION (Continued)
Mains connections.
Do not connect the mains supply to the panel until you are fully conversant with the layout and
features of the equipment.
A rating plate is fitted in the bottom right hand corner of the panel describing the nature of the supply
permitted.
The incoming mains supply should be brought into the panel in the bottom right hand corner, via the
knockout provided.
A suitable cable gland must be used to secure the outer sheath of the cable used. The earth must
first be connected to the primary earth stud (peg) marked with a
symbol using the ring
crimp provided.
Sufficient earth lead should be left to allow Live and Neutral connections to be accidentally pulled
from terminal block, while leaving earth connection intact. Secondary earths may be connected to
the brass earthing block.
Field devices
Sensors, call points and input/output devices are supplied with full installation instructions.
Warning
High voltage testing of the wiring must be carried out
before
the control panel and any devices are
connected.