4.3 Positioning
Transport to installation site with fork-lift or similar lifting device
1
3
5
6
If the height of the boiler prevents it from being transported as a single unit:
❒
⇨ See "Disassemble for easier transport to the installation site" [page 57]
Use a crane to transport to transport to installation site (only wit PE1 Pellet):
2
3
3
4
5
6
4.4 Temporary storage
If the system is to be assembled at a later stage:
❒ Store components at a protected location, which is dry and free from dust
➥ Damp conditions and frost can damage components, particularly electric ones!