10.2 Starting the engine with jump leads
NOTICE!
A wrong connection will cause
severe damage in the electric
system.
– Bridge the machine only with a
12 Volt auxiliary battery.
1.
Connect the plus pole of the external bat-
tery first with the plus pole of the vehicle
battery using the first jump lead.
2.
Then connect the second battery cable first
to the minus pole of the current supplying
auxiliary battery and then to engine or
chassis ground, as far away from the bat-
tery as possible.
3.
.
NOTICE!
Danger of damage to the elec-
tronic system!
If no powerful consuming device is
switched on, voltage peaks may
occur when separating the con-
necting cables between the bat-
teries, which could damage elec-
trical components.
4.
Once the engine is running switch on a
powerful consumer (working light, etc.).
5.
After starting disconnect the negative poles
first and the positive poles after.
6.
Switch off the consumer.
Fig. 196
Troubleshooting – Starting the engine with jump leads
BW 100 ADM-5
203
Summary of Contents for BOMAG BW 100 ADM-5
Page 9: ...1 Introduction Introduction BW 100 ADM 5 9 ...
Page 13: ...2 Technical data Technical data BW 100 ADM 5 13 ...
Page 18: ...Technical data Noise and vibration data BW 100 ADM 5 18 ...
Page 19: ...3 Concerning your safety Concerning your safety BW 100 ADM 5 19 ...
Page 65: ...4 Indicators and control elements Indicators and control elements BW 100 ADM 5 65 ...
Page 82: ...Indicators and control elements Outside of machine BW 100 ADM 5 82 ...
Page 83: ...5 Checks prior to start up Checks prior to start up BW 100 ADM 5 83 ...
Page 97: ...6 Operation Operation BW 100 ADM 5 97 ...
Page 128: ...Operation Emergency procedures BW 100 ADM 5 128 ...
Page 129: ...7 Loading transporting the machine Loading transporting the machine BW 100 ADM 5 129 ...
Page 139: ...8 Maintenance Maintenance BW 100 ADM 5 139 ...
Page 194: ...Maintenance As required BW 100 ADM 5 194 ...
Page 195: ...9 Setting up refitting Setting up refitting BW 100 ADM 5 195 ...
Page 200: ...Setting up refitting Edge cutter mounting and removing tools BW 100 ADM 5 200 ...
Page 201: ...10 Troubleshooting Troubleshooting BW 100 ADM 5 201 ...
Page 206: ...Fuse Amperage Designation F00 80 A Main fuse Troubleshooting Fuse assignment BW 100 ADM 5 206 ...
Page 212: ...Troubleshooting Trouble shooting ECONOMIZER BW 100 ADM 5 212 ...
Page 213: ...11 Disposal Disposal BW 100 ADM 5 213 ...
Page 215: ......
Page 216: ......