8.10.3 Checking the travel lever control
1.
‘Parking the machine in secured condition’
.
2.
Move the travel lever forwards, backwards
and to braking position. Check the function,
for ease of movement, clearance and
damage.
3.
In case of malfunction perform trouble-
shooting and replace the corresponding
parts.
4.
Only operate the machine after it has been
repaired.
8.10.4 Checking the ROPS
All bolted connections must comply with the
specifications and should be absolutely tight
(observe the tightening torques).
Screw and nuts must not be damaged, bent or
deformed.
Unusual movements and noises (vibrations)
during operation are signs for damage or loos-
ened fastening elements.
1.
Inspect the ROPS structure for cracks, cor-
rosion, damage and missing fastening
parts.
2.
Check the fastening screws for the ROPS
to the operator’s stand for tight fit.
3.
Check the rubber buffers of the operator’s
platform suspension for condition and tight
fit.
4.
Check the condition and fastening of the
seat belts.
B-ELE-0262
Fig. 163
Maintenance – Every 1000 operating hours
BW 100 ADM-5
173
Summary of Contents for BOMAG BW 100 ADM-5
Page 9: ...1 Introduction Introduction BW 100 ADM 5 9 ...
Page 13: ...2 Technical data Technical data BW 100 ADM 5 13 ...
Page 18: ...Technical data Noise and vibration data BW 100 ADM 5 18 ...
Page 19: ...3 Concerning your safety Concerning your safety BW 100 ADM 5 19 ...
Page 65: ...4 Indicators and control elements Indicators and control elements BW 100 ADM 5 65 ...
Page 82: ...Indicators and control elements Outside of machine BW 100 ADM 5 82 ...
Page 83: ...5 Checks prior to start up Checks prior to start up BW 100 ADM 5 83 ...
Page 97: ...6 Operation Operation BW 100 ADM 5 97 ...
Page 128: ...Operation Emergency procedures BW 100 ADM 5 128 ...
Page 129: ...7 Loading transporting the machine Loading transporting the machine BW 100 ADM 5 129 ...
Page 139: ...8 Maintenance Maintenance BW 100 ADM 5 139 ...
Page 194: ...Maintenance As required BW 100 ADM 5 194 ...
Page 195: ...9 Setting up refitting Setting up refitting BW 100 ADM 5 195 ...
Page 200: ...Setting up refitting Edge cutter mounting and removing tools BW 100 ADM 5 200 ...
Page 201: ...10 Troubleshooting Troubleshooting BW 100 ADM 5 201 ...
Page 206: ...Fuse Amperage Designation F00 80 A Main fuse Troubleshooting Fuse assignment BW 100 ADM 5 206 ...
Page 212: ...Troubleshooting Trouble shooting ECONOMIZER BW 100 ADM 5 212 ...
Page 213: ...11 Disposal Disposal BW 100 ADM 5 213 ...
Page 215: ......
Page 216: ......