15.F CONTROL OF ALARMS
ALARM FOR MISFUNCTIONING OF MAIN MOTOR-FAN (LAF)
This alarm can be simulated by disconnecting the power cables of the main motor-fan. When the isolator is
switched o
n and the “stand-by” period is over, check that the red light of the relevant alarm and the visual
and sound (buzzer) signals start.
ALARM FOR MISFUNCTIONING OF SECONDARY MOTOR-FAN (EXHAUST)
Also this alarm can be simulated by disconnecting the power cables of the main motor-fan. . When the
isolator
is switched on and the “stand-by” period is over, check that the red light of the relevant alarm and the
visual and sound (buzzer) signals start.
ALARM FOR REDUCTION OF THE EXHAUST DUCT CAPACITY
To verify this alarm, clog the exhaust duct gradually at the end of stand-by period and check that the red light
of the relevant alarm and the visual and sound (buzzer) signals start. Furthermore check that when the
clogged duct is cleared, the alarm stops.
ALARM FOR OPENING OF THE FRONT WINDOW OF THE ISOLATOR
To verify this alarm it is enough you move the front window from its standard work position removing the four
knobs and check that the red light of the relevant alarm and the visual and sound (buzzer) signals start. Re-
position the window in its standard work position and check that the alarm stops.
ALARM FOR REDUCTION OF LAMINAR AIRFLOW VELOCITY IN THE WORK CHAMBER
During the normal working of the isolator, cover the work surface almost completely with a PVC or cardboard
sheet and check that the relevant red light switches on. When the correct operating conditions of the laminar
airflow are restored, the alarm will stop.
OTHER ALARMS
With the help of FASTER’s technicians also the alarms for LAF and protection barrier velocity below the
minimum threshold or over the maximum threshold can be checked
Summary of Contents for GLOVEFAST ASEPTIC
Page 9: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 9 of 65...
Page 26: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 26 of 65 1 2...
Page 46: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 46 of 65...
Page 48: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 48 of 65 15 J DIAGRAM FOR MAINTENANCE OPERATIONS...
Page 49: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 49 of 65 16 FRONTAL DIAGRAM...
Page 50: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 50 of 65 16 A SIDE DIAGRAM...
Page 54: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 54 of 65 18 WIRING DIAGRAM...
Page 55: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 55 of 65...
Page 56: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 56 of 65...
Page 57: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 57 of 65...
Page 58: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 58 of 65...
Page 59: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 59 of 65...
Page 60: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 60 of 65...
Page 61: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 61 of 65...
Page 62: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 62 of 65...
Page 63: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 63 of 65...
Page 64: ...a D GROUP Company 0254EN Rev 06 09 2019 Page 64 of 65...