Prodigy FlyPipe Installation Guide
Attach TwinLine Clamps
Once you have positioned your hoist, you must run the TwinLine and TwinLine clamps up to the
strut channel. To secure the clamps to your strut channel, perform the following steps. If you are
installing helix cable management, you should hang the cable assembly before attaching the
TwinLine clamp for the second set of lift lines that run through the cable assembly. For
instructions on hanging the cable assembly, refer to
Hang Helix from Upper Attachment Points
.
Note:
The hoist must rest in a position that will allow for the entire intended travel
distance of wire rope plus 41 cm (16 in) minimum dead hang to be run up when
attaching the TwinLine clamps.
1. Run the TwinLine and TwinLine clamp up to the strut channel attached to the building
structure.
2. Rotate the channel nut so the long sides are parallel with the run of strut channel. This
ensures that the nut can be inserted into the channel.
3. Insert the nut into the strut channel.
Tighten socket
cap screw
4. Using a 10 mm (3/8 in) hex key, tighten the socket cap screw so the channel nut rotates
90 degrees against the walls of the strut channel and until the nut is snug against the
bottom of the strut channel. The recommended torque range for this is 68–88 Nm (50–
65 ft-lb).
Note:
TwinLine clamps can be installed perpendicular or parallel to the strut channel.
However, the clamps must always be installed perpendicular to the batten or body of
the hoist.