46
9395P 250 kVA / 275 kVA / 300 kVA
User’s and Installation Guide
4.7.3
X-Slot Connections
For installation and setup of an X-Slot card, contact an Eaton service representative .
To install wiring to connections:
1.
If not already installed, install the LAN and telephone drops.
2.
Unfasten the front door latch and swing the door open (see Figure 4
‐
2).
3.
Remove the UPS cabinet interface entry conduit landing plates to drill or punch holes (see Figure 4
‐
4).
4.
Reinstall the interface entry plates and install the conduit.
5.
Route and install the LAN, telephone, and other cables to the appropriate X-Slot cards. See Figure 4
‐
13
and Figure 4
‐
19 for X-Slot communication bay locations.
6.
Close the front door and secure the latch.
7.
Refer to the manual supplied with the X-Slot card for operator instructions.
X-Slot Communication Bay 1
X-Slot Communication Bay 2
X-Slot Communication Bay 3
X-Slot Communication Bay 4
Figure 4‐19. X-Slot Communication Bays
NOTE
LAN and telephone drops for use with X-Slot cards must be provided by the customer.
When installing external wiring to X-Slot cards, conduit must be installed to the UPS cabinet.
When installing internal wiring to X-Slot terminals, route the wiring through the internal
opening in the X-Slot communication bay.
•
•
Summary of Contents for Power Xpert 9395P 250 kVA
Page 1: ...User s and Installation Guide Power Xpert 9395P UPS 250 kVA 275 kVA 300 kVA...
Page 2: ......
Page 3: ...Power Xpert 9395P UPS 250 kVA 275 kVA 300 kVA User s and Installation Guide...
Page 168: ......
Page 169: ......
Page 170: ...614 01919 00...