10
−
15
EATON
Powerware 9315 Parallel Capacity/Redundant System
164201150 Rev. E
www.powerware.com
10.4
Transfer to Maintenance Bypass
NOTE:
Refer to Appendix A for location of Maintenance Bypass key switch.
1.
Ensure power is supplied to the MBP breaker input before attempting transfer
to maintenance bypass.
2.
On 1200A SBM, ensure SBM is on bypass. On 2000A SBM ensure that SBM
CBS breaker is open or system is not on inverter.
3.
On SBM, turn the Maintenance Bypass key switch to
the left (To Maintenance)
momentarily.
4.
Observe MBP closes and MIS opens. System is now on maintenance bypass.
5.
To shutdown SBM and UPMs, follow procedure under
SBM Shutdown to
Bypass.
WARNING
Power is present at SBM, CBP, and FBP inputs until upstream
SBM bypass input feeder circuit breaker is opened.
6.
On SBM, open CBP and FBP breakers.
10.5
Transfer from Maintenance Bypass
NOTE:
Refer to Appendix A for location of Maintenance Bypass key switch.
1.
If system was shutdown, follow
Manual Start
or
Auto Start
procedure to start
system.
2.
Ensure SBM is on bypass.
3.
On SBM, turn the Maintenance Bypass key switch to
the right
(From Maintenance) momentarily.
4.
Observe MIS closes and MBP opens. System is now in normal mode.
Summary of Contents for 9315
Page 1: ...Powerware 9315 UPS Parallel Capacity Redundant System Installation and Operation Manual ...
Page 136: ......
Page 205: ......
Page 206: ...164201150 Rev E 164201150E ...