A−51
EATON
Powerware 9315 Parallel Capacity/Redundant System
164201150 Rev. E
www.powerware.com
1.
Two redundant PowerNet control networks connect the UPMs to each other and the UPMs
to the SBM. Each network requires only one shielded twisted pair of wires and one twisted
pair of wires for the redundant power supplies. The control wiring is connected at J2 of
the CAN interface. See drawing below.
2.
Refer to sheets 2 and 3 for location of the CAN A and CAN B Logic Boards.
3.
Use Class 1 wiring methods (as defined by the NEC) for control wiring. Install the control
wiring in separate conduits from the power wiring. Install the twisted pair of each
redundant PowerNet network in separate conduits. The wire should be rated at 24 volts,
1 amp minimum. The recommended wire for the PowerNet network is shielded 20 gauge
twisted pair Belden 8762 or equivalent. The recommended wire for the power supplies is
14 gauge twisted pair
4.
Control wiring run may not exceed 100 meters.
5.
Connect control wiring to the removable portion of the terminal block.
6.
Terminate each redundant PowerNet network at the end modules in the system. Refer to
drawing 164201150−13, sheet 2 for typical termination points.
7.
Refer to applicable chapters for information about installing control wiring.
DESCRIPTION:
DRAWING NO:
SHEET:
UPM CAN INTERFACE:
POWERWARE 9315−625/750 UPMs
1 of 3
164201150−15
J2 CAN Interface
Connection
Summary of Contents for 9315
Page 1: ...Powerware 9315 UPS Parallel Capacity Redundant System Installation and Operation Manual ...
Page 136: ......
Page 205: ......
Page 206: ...164201150 Rev E 164201150E ...