User Manual 200 kVA-1200 kVA UPS
3 Installation
23
Fig. 3-7 Location and size of 6 holes for 200 kVA/250 kVA/300 kVA (bottom view)
Fig. 3-8 Location and size of 8 holes for 400 kVA/500 kVA/600 kVA (bottom view)
Step 2
: locate the UPS to the final installation location.
Step 3
: lift the equipment with the forklift until the bottom of the case is suspended.
Step 4
: finely adjust the case to align the expansion bolts with the holes below.
Step 5:
fix the front and back bolts of the case to the ground with expansion bolts.
Step 6:
reinstall the removed bottom baffle to the bottom side of the equipment.
3.2. 3 Installation of Battery
During the installation design of UPS system, please use batteries approved by supplier. Without permission, it is
forbidden to use batteries of other brands because UPS is excluded from the warranty for damage of UPS caused
by batteries of other brands. If the batteries of other brands are used, please contact local distributor.
For the installation method, please see the battery installation instructions shipped with the battery.
CAUTION
Summary of Contents for EA990 Super
Page 1: ...200 kVA 1200 kVA ...