Commissioning
Edition 03 / 69 06 898
42
FTS 8000
9. Switch on the main switch in the technical room. Acknowledge the alarm on the
touchscreen.
10. Turn on the "System on" key switch.
Acknowledge the alarm on the
touchscreen.
11. The start screen appears automatically
on the cabinet touchscreen. Log on the
user.
12. Slowly open both main ball
valves on the gas control
paths. Pressure spreads
throughout the system.
13. If necessary, acknowledge
faults in the technical room.
The fire simulation system is
ready for operation.
4.5
Checklist - Daily commissioning
Fig. 54 Switch on the main switch
Fig. 55 Acknowledge the alarm
i
i
NOTICE
A checklist for the daily commissioning process is given in the "Forms" chapter of this
customer documentation.
Fig. 56 Turn on the "System on" key switch