(Refer to figure 27)

1.

Electrical box

2.

Cover of electrical box

3.

Cover for servicing

4.

Inspection cover

5.

Points to be noted when providing services

Cautions for check operation

• If operated within about 12 minutes after power supply has been 

applied to the indoor unit and outside unit, H2P will turn ON but 
the compressor does not start running. Before start operation, 
make sure that the LED display is correct referring to the table (6) 
of “

11-3 Check operation

”.

• The system may require up to 10 minutes until it can start the 

compressor after an operation start. This is a normal operation to 
equalize the refrigerant distribution.

• The check operation does not provide any means of checking the 

indoor units individually. For that purpose, perform normal opera-
tion using the remote controller after the check operation.

• Check operation is not possible in other modes such as collection 

mode.

• If the setting of indoor remote controller is changed before the 

check operation, it may not be performed correctly and malfunc-
tion code “UF” may be displayed.

Remote controller displays malfunction code

11-4 Check of normal operation

After the check operation is completed, operate the unit normally. 
(Heating is not possible if the outdoor temperature is 24°C or higher. 
Refer to the Operation manual.)
Check the below items.

Make sure the indoor and outside units are operating normally 
(If a knocking sound can be heard in the liquid compression of 
the compressor, stop the unit immediately and then energize 
the heater for a sufficient length of time before restarting the 
operation.)

Run each indoor unit one at a time and make sure the corre-
sponding outside unit is also running.

Check if cold (or hot) air is coming out of the indoor unit.

Press the fan direction and fan strength buttons on the indoor 
unit to check if they operate properly.

Caution

Cautions for normal operation check

Once stopping, the compressor will not restart in about 5 min-
utes even if the 

Run/Stop

 button of an indoor unit in the same 

system is pressed.

When the system operation is stopped by the remote control-
ler, the outside units may continue operating for further 5 min-
utes at maximum.

If the system has not undergone any check operation by the 
test operation button since it was first installed, an malfunction 
code “U3” is displayed. In this case, perform check operation 
referring to “

11-3 Check operation

”.

After the test run, when handing the unit over to the customer, 
make sure the EL. COMPO. BOX cover, the inspection door, 
and the unit casing are all attached.

(7) • Using the push button switches (BS1 - 

5) on the P-panel (A1P) of outside unit, 
carry out a local setting, if necessary.

• 

In case of an installation of multiple 

outside units, carry out the setting on 
the master unit.

(Setting on the slave unit becomes 

invalid.)

Always carry out the setting 

only after the 

power supply has been applied

.

For the method of setting, refer to the label of 

Points to be noted when providing ser-

vices

” attached to the cover of electrical box 

(shown in the figure 27) of the outside unit.
(After setting, record the details of that setting 

to the label of “Points to be noted when pro-
viding services” without fail.)

(8)Check all shutoff valve is opened. 

If some shutoff valve is closed, open them.
(Refer to “

9-10 Shutoff valve operation 

procedure

”.)

[CAUTION]

Do not leave any shutoff valve closed. 
Otherwise the compressor will fail.

For Heat recovery system of cooling and 

heating:
Open all stop valves on the suction side, 

discharge gas side and liquid side.

For cooling and heating switching operation 
system:

Open the stop valves on discharge gas side 

and liquid side. 

(Keep the stop valve on 

suction side fully closed.)

(9)Perform the check operation following the 

instructions printed on the [Service 
Precautions] label.

If you push the test run button (BS4) on the 

P-panel (A1P) of the outside unit. 
for 5 seconds, the test run starts.

If you want to interrupt the test run, push the 

RETURN button (BS3) on P-panel (A1P) of 
the outside unit. The system continues resid-

ual operation for about 1 minute (maximum 

10 minutes) and then stops.
(During test run, you cannot stop it by a com-

mand from a remote controller.)

You need to perform the above settings 
on the PCB by accessing the PCB through 

the inspection cover on the switch box 

cover.

Malfunc-

tion code

Installation error

Remedial action

E3
E4
F3
F6

UF
U2

The shutoff valve of an 
outside unit is left 
closed.

Open the shutoff valve.

U1

The phases of the 
power to the outside 
units are reversed.

Exchange two of the three 
phases (L1, L2, L3) to make a 
positive phase connection.

U3

The check operation
 is not completed.

Complete the check operation.

U1
U2
U4

No power is supplied to 
an outdoor or indoor 
unit (including phase 
interruption).

Check if the power wiring for the 
outside units are connected cor-
rectly.
(If the power wire is not con-
nected to L2 phase, no malfunc-
tion display will appear and the 
compressor will not work.)

UF

Incorrect transmission 
between units

Check if the refrigerant piping line 
and the unit transmission wiring 
are consistent with each other.

E3
F6

UF
U2

Refrigerant overcharge

Recalculate the required amount 
of refrigerant from the piping 
length and correct the refrigerant 
charge level by recovering any 
excessive refrigerant with a 
refrigerant recovery machine.

E4
F3

Insufficient refrigerant

Check if the additional refrig-
erant charge has been fin-
ished correctly.

Recalculate the required 
amount of refrigerant from the 
piping length and add an ade-
quate amount of refrigerant.

U7
UF

If an outdoor multi ter-
minal is connected 
when there is one out-
side unit installed

Remove the line from the outdoor 
multi terminals (Q1 and Q2).

UF

E4

The operation mode on 
the remote controller 
was changed before 
the check operation.

Set the operation mode on all 
indoor unit remote controllers to 
“cooling.”

HJ

The heat source water 
is not circulating.

Make sure that the water pump 
is running.

01_EN_3P153897-8L.fm  Page 15  Friday, July 11, 2008  5:04 PM

Summary of Contents for VRV-WIII

Page 1: ...II Manuale di installazione Condizionatore d aria a sistema VRVWIII VRVWIII Installatiehandleiding Airconditioner met VRVWIII Systeem Manual de instala o Ar condicionado VRVWIII System VRVWIII English...

Page 2: ...RXYQ54PY1 E RTSYQ10PY1 RTSYQ14PY1 RTSYQ16PY1 RTSYQ20PY1 RTSQ8PY1 RTSQ10PY1 RTSQ12PY1 RTSQ14PY1 RTSQ16PY1 BTSQ20PY1 REYQ8PY1 REYQ10PY1 REYQ12PY1 REYQ14PY1 REYQ16PY1 REYQ18PY1 REYQ20PY1 REYQ22PY1 REYQ24...

Page 3: ...UT D UNIT TO MULTI UNIT IN D OUT D BS F1 F1 F2 F2 F1 F2 F1 F2 F1 F2 F1 F2 IN D OUT D BS F1 F1 F2 F2 F1 F2 IN D OUT D BS F1 F1 F2 F2 F1 F2 8 11 9 10 6 4 Heat recovery system Heat pump system 7 A1P A B...

Page 4: ...OFF ON O U T I N F1 F2 P1 P2 P1 P2 1 figure 16 1 2 3 13 14 15 4 17 16 18 11 10 9 6 5 8 4 7 12 figure 19 figure 18 1 2 6 3 3 4 5 1 2 F1F2 F1F2 F1F2 F1F2 F1F2 figure 14 Heat pump system Heat recovery s...

Page 5: ...t pump system Heat recovery system figure 24 4 5 3 2 1 figure 25 figure 26 1 1 2 2 3 3 4 4 5 6 Heat recovery system Heat pump system figure 23 figure 27 1 2 3 4 5 1 15 2 3 3 C arrow view D arrow view...

Page 6: ...refully before installing air conditioning unit and be sure to install it correctly After completing installation conduct a trial operation to check for faults and explain to the customer how to opera...

Page 7: ...nstall the air conditioner in the following locations 1 Where there is a high concentration of mineral oil spray or vapour e g a kitchen Plastic parts will deteriorate parts may fall off and water lea...

Page 8: ...1 The foundation is strong enough to support the weight of the unit and the floor is flat to prevent vibration and noise generation 2 Consider the space required for refrigerant piping work when insta...

Page 9: ...pipe made of a material other than stainless steel may result in corrosion of the pipe Take preventive measures as necessary for example by insulat ing the connection on the water pipe The connection...

Page 10: ...ce should be activated during operation remove the cause without fail before restarting the operation If the freezing protection device has been once acti vated a partial freezing has occurred If you...

Page 11: ...ntial start refer to chapter Examples For connection wiring to the central remote controller refer to the installation manual of the central remote controller 8 2 Power circuit and cable requirements...

Page 12: ...ge Use insulated wires of the size as mentioned below having rated voltage of 250 V or higher For single core 1 25 mm or larger conduit pipe work For multiple cores 0 75 mm or larger The wiring for pu...

Page 13: ...ution Precautions when laying power wiring Use crimp style terminals for connections to the power terminal block When none are available follow the instructions below Do not connect wiring of differen...

Page 14: ...n 30 against horizontal surface 3 Horizontal surface 7 The outside unit multi connection piping kit that is sold separately as an option BHFP22MA56 84 BHFP26MA56 84 is necessary for the multi installa...

Page 15: ...f outside units See the installation manual attached to the kit with attention to installation restrictions described in connecting the refrigerant piping when installing 1 To avoid the risk of oil de...

Page 16: ...ed to downstream For the gas piping size in case of 2 tube piping between refrigerant branching kit BS unit and refrigerant branching kit select the size of suction gas piping The size of connection p...

Page 17: ...40 m Increase the liquid and suction gas pipe size as follows 9 5 12 7 12 7 15 9 15 9 19 1 19 1 22 2 22 2 25 4 28 6 31 8 34 9 38 1 a A B C D E F G b c d e f g h i j k l m n 1 2 3 4 5 6 7 8 p REFNET jo...

Page 18: ...ING 3 Make sure there is no faulty refrigerant piping See 9 REFRIGERANT PIPING 4 Make sure piping size is correct See 9 1 Selection of piping material 5 Make sure insulation work is done See 9 7 Pipe...

Page 19: ...both liquid and gas is opened See the Shutoff valve operation procedure in chapter 9 10 2 Additional refrigerant charge The amount of refrigerant to be added to the unit should be written on the incl...

Page 20: ...supply has been applied For the method of setting refer to the label of Points to be noted when providing ser vices attached to the cover of electrical box shown in the figure 27 of the outside unit A...

Page 21: ...n accordance with steps 1 to 4 below and take whatever action is necessary to comply 1 Calculate the amount of refrigerant kg charged to each system separately Note Where a single refrigerant facility...