12
|
Commissioning
Installer reference guide
226
EBLA04~E23V3 + EDLA04~E23V3
Daikin Altherma 3 M
4P685228-1A – 2022.05
Only for models with integrated backup heater (F1B: field supply), or if the external backup
heater kit (F1B: factory-mounted in the backup heater kit) is installed:
Backup heater circuit breaker
F1B is turned ON.
Only for tanks with built-in booster heater:
Booster heater circuit breaker
F2B (field supply) is turned ON.
The correct pipe size is installed and the
pipes
are properly insulated.
There are no
water leaks
inside the outdoor unit.
The
shut-off valves
are properly installed and fully open.
The
automatic air purge valve
is open.
The
pressure relief valve
purges water when opened. Clean water MUST come out.
The
minimum water volume
is guaranteed in all conditions. See "To check the water
(if applicable) The
domestic hot water tank
is filled completely.
12.4 Checklist during commissioning
The
minimum flow rate
is guaranteed in all conditions. See "To check the water volume
and flow rate" in
To perform an
air purge
.
To perform a
test run
.
To perform an
actuator test run
.
Underfloor screed dryout function
The underfloor screed dryout function is started (if necessary).
12.4.1 Minimum flow rate
Purpose
For a correct operating unit, it is important to check if the minimum flow rate is
reached. If needed, modify the bypass valve setting.
If operation is…
Then the minimum required flow rate
is…
Cooling
10 l/min
Heating
6 l/min
BUH operation
12 l/min
Heating defrost
12 l/min
DHW
25 l/min
To check the minimum flow rate
1
Check the hydraulic configuration to find out which space
heating loops can be closed by mechanical, electronic, or other
valves.
—
2
Close all space heating loops that can be closed.
—
Summary of Contents for EBLA04E2V3
Page 280: ...14 14 ...
Page 281: ......
Page 282: ......
Page 283: ......
Page 284: ...4P685228 1A 2022 05 Copyright 2022 Daikin Verantwortung für Energie und Umwelt ...