Page 17
Hydraulic System Troubleshooting, Testing and
Adjustment
Return to Master Table of Contents
PUMP INPUT POWER CONTROL
PUMP REGULATOR ADJUSTMENT
To perform these adjustments accurately the use of a flow meter is strongly recommended, as is consulting
the factory (before starting work) to validate the need for making regulator adjustments. Vent hydraulic
pressure from the reservoir before breaking the seal on fittings to install the flow meter kit. (Refer to the
"Flow meter Installation and Testing" procedure.)
Use a scribe or other permanent marker to identify a reference point on adjusting screws with a
corresponding reference on the body of the valve. The adjustment process affects a complex balance and
could require some time to complete. If adjustment has to be interrupted or postponed, reference marks at
the adjustment point allow immediate restoration of original performance.
This adjustment procedure is normally performed:
•
If the engine is being consistently overloaded (and engine troubleshooting shows engine
performance to be at or above rated output);
•
If reduced cylinder speed and diminished work performance provide an indication that rated,
maximum pump flow may not be available (and all other troubleshooting gives no indication of
other flaws or hydraulic system defects);
•
If pump output is out of balance and one pump is failing to keep up with the output flow of the
other.
To check pump imbalance without a flow meter, travel the excavator forward on flat, level terrain. If the
machine veers off despite neutral control input and even, balanced track adjustment, the pump which
supplies output to the track frame toward which the excavator is veering is weak.
WARNING!
This procedure should be done with two people. To reduce the chance of accident or unintended
start-up, one person should remain at the operator’s control stand while checks and
adjustments are made.
IMPORTANT
Before starting this procedure or going on to make any changes of adjustment settings,
•
Verify engine output to the rated speed - 2,150 ±50 RPM.
•
Permanently mark setscrew positions at the current regulator control setting.
Summary of Contents for Solar 420LC-V
Page 1: ...Return to Master Table of Contents 1HYDRAULICS...
Page 33: ...S0703010K Page 2 Accumulator TABLE OF CONTENTS General Description 3 Specifications 4...
Page 43: ...S0704090K Page 8 Center Joint Swivel...
Page 63: ...S0705000 Page 20 Cylinders Return to Master Table of Contents...
Page 70: ...S0707260 Page 7 Swing Motor...
Page 74: ...S0707260 Page 11 Swing Motor SPECIAL TOOLS Figure 5...
Page 91: ...S0707260 Page 28 Swing Motor...
Page 103: ...S0707365 Page 12 Travel Motor With Gearbox A6V160HD PARTS LIST Travel Motor Figure 12 HTS6331...
Page 107: ...S0707365 Page 16 Travel Motor With Gearbox A6V160HD Travel Motor Control HTS6331 Figure 14...
Page 136: ...S0707365 Page 45 Travel Motor With Gearbox A6V160HD 29 Remove gasket Figure 91 Figure 91 3061...