Effective October, 2000
Page 16
Before proceeding, identify the section(s) within
the Step that apply to the Breaker being
Retrofitted.
Step 8:
Installing the Breaker Mounted CPT
A. Align the CPT with the holes in the CPT
Mounting Bracket as shown. Secure the CPT
to the mounting bracket using the (4)
.190-32
×
.500" screws, (8) flat washers,
(4) lock washers, and (4) nuts supplied.
B. Align the Glass Ploy Insulation with the holes in
the CPT Mounting Bracket as shown. Secure
the CPT to the mounting bracket using the (2)
.190-32
×
.625" nylon screws, (2) nylon flat
washers, (2) steel flat washers, (2) lock
washers, and (2) nuts supplied. Note that the
screws are inserted thorough the Glass Poly
Insulation first and then through the CPT
Mounting Bracket. The nylon flat washers
MUST BE used between the screw head and
the Glass Poly Insulation.