03/2008 - Art. Nr. 13 013 477C
4
Installation
Assembly
Boiler face
• Prepare face according to the
enclosed space requirement diagram.
If required, insert a counter face plate
(option).
• Fill in space
1
with recommended
heat-resistant material or material
supplied by the boiler manufacturer.
Do not obstruct combustion
chamber pressure take-off
pF
.
Combustion head
• Place combustion head for gas train
horizontal connection to the
right
or
left.
• Fit and secure combustion head with
its seal on boiler face.
• Check for possible leaks.
Gas train
• Check presence and position of O-ring
B
in manifold
C
flange.
• When fitting gas train, valve coils must
be in the
vertical top position
.
Important
When using a left-mounted VGD gas
train, it is necessary to pivot the SKP75
regulator 180°.
To do this:
• Remove the SKP75 regulator.
• Remove the connector (3P+T) on the
side of the regulator and remount it
opposite.
Seal off the old position of the
connector.
• Refit the regulator once it has been
pivoted a half turn (180°).
Burner body
This must only be installed with
volute
casing downwards
or upwards (see
space requirements).
No other assembly positions are
authorised.
• Hook burner body on to combustion
head using fixed spindle
F
located
opposite gas train.
• Connect both ignition cables and
ionization probe cable.
• Close burner body with mobile spindle
E
.
• Fit safety screw
D
.
• Check for possible leaks.
Summary of Contents for C120 GX507/8
Page 40: ...03 2008 Art Nr 13 013 477C 40 1 pF VGD SKP 180 SKP 3 SKP 180 F D...
Page 42: ...03 2008 Art Nr 13 013 477C 42...
Page 44: ...03 2008 Art Nr 13 013 477C 44 5 1 1 6 F 5 6 5 0 5 3 1 3 6 5 6 3 0 3...
Page 54: ...03 2008 Art Nr 13 013 477C 54 D 1 RTC 2 J1 1 RTC 1 pF 2...