Installing Subracks and PSUs in an Equipment Rack
I
NSTALLING
S
UBRACKS
AND
PSU
S
IN
AN
E
QUIPMENT
R
ACK
The following sections tell how to install ION-E WCS and e-POI subracks and the PSU in an equipment rack.
Rack-Mounting the Subracks and PSU
The following graphic shows two configurations for mounting ION-E subracks and PSUs in an equipment
rack. In any ION-E installation, the following rules must be followed:
•
PSUs must be mounted above the WCS for support.
•
1 RU of air space required above the PSU.
•
Support rails are required for WCS Subracks.
•
Support rails are required for e-POI Subracks.
•
Support rails must not block airflow.
As with any piece of IT equipment, placing the ION-E system connection behind a secure firewall is highly
recommended
Disconnect all input to the PSU before adding it to or removing it from an equipment rack.
1 RU air space required
4
1
2
2
3
1 RU air space required
1
2
3
2
4
1
e-POI Subrack (4RU high)
2
Support rail
3
Power Supply Unit (PSU)
4
WCS Subrack (WCS-2 is 2 RU high and WCS-4 is 4RU high)