Initialisation steps in daily use
Once the system is configured and a satellite profile is active, the startup sequence is as
follows:
• ACU POST
• ADU Initializing
• ADU SW upload (If the software versions in the ADU and ACU are not the same, a
software update is done during startup.)
• ADU POST
• READY
• POINTING ANTENNA
• ACQUIRING SIGNAL
• TRACKING
5.3.4
SAILOR 900 Ka operational
When the display shows
TRACKING
.
MDM: NETOK
and the LED
Logon
is steady green
the system is operational.