Installation of the ADU
3-18
Chapter 3: Installation
98-148248-C
The antenna comes with a lifting harness already fitted. The lifting harness is provided
solely for the purpose of installation the antenna. The belt of fibre material prevents the
antenna from toppling during the lifting process.
3.3.2.1 Lifting Harness – Declaration of Conformity
The lifting harness (Cobham SATCOM part number TT 48-149056) is designed, tested and
conforms to the requirements for lifting equipment in DIRECTIVE 2006/42/EC OF THE
EUROPEAN PARLIAMENT AND OF THE COUNCIL of 17 May 2006 on machinery, and
amending Directive 95/16/EC (recast).
The Working Load Limit (WLL) is defined as 40 kg. The harness may only be used for lifting
the ADU.
Figure 3-18: Use of the lifting harness and tag lines for safe hoisting
WARNING!
Use the lifting harness only to lift the antenna. Do not lift other
objects or persons with the harness.
Lifting harness with 4
lifting straps
Tag lines
Summary of Contents for SAILOR 60 GX
Page 1: ...Cobham Public SAILOR 600 VSAT Ka SAILOR 600 VSAT Ka High Power Installation manual...
Page 116: ...Software update 8 12 Chapter 8 Service 98 148248 C Figure 8 11 Verifying software update...
Page 181: ...Telenor antenna approval G 4 Appendix G Approvals 98 148248 C...
Page 192: ...98 148248 C www cobham com satcom Cobham Public...