Page 22
Model 21 -CET-8 Service Manual
3. Check all lines and connections for leakage, both inside and outside the
steamer.
4. If Final Setup and Checkout will be performed next, leave the right side
panel off; otherwise, replace the side panel and secure it to the unit with
the two
screws (Figure 2-16).
NOTE:
If the steamer has not been mounted yet:
For surface mounting, return to page 12, step 5, and finish the
mounting procedure.
For equipment stand installation and steamer mounting, return to
page 13, step 2, install the stand and mount the steamer.
Final Setup and Checkout
The Final Setup and Checkout procedures prepare a recently installed or
repaired SteamCraft 3.1 for operation. The procedures check proper electrical,
water, and drain connections to the SteamCraft 3.1, and verify basic steamer
operation.
Model 21-CET-8 SteamCraft 3.1's have an electronic control panel with a key
pad timer control. This control panel is illustrated in Figure 2-23 on page 23.
An electro-mechanical control panel is also available. This panel has a dial
timer control, as illustrated in Figure 2-24 on page 26. There are a few
operating differences between steamers with the dial timer controls and
steamers with the key pad controls. To avoid confusion during testing, there
are two sets of testing instructions: one labeled Operating Tests - Key Pad
Control Panel for the electronic control panel, and one labeled Operating
Tests-Dial Timer Control Panel for the electro-mechanical control panel.
After performing the setup procedure, perform the test procedure appropriate
to the control panel on the SteamCraft 3.1 being tested.
Setup and Blowdown Inspection - All SteamCraft 3.1's
This procedure
is appropriate for SteamCraft 3.1's with either key pad control
panels or dial timer control panels. Read through all steps of this procedure
before starting. Complete this setup procedure before starting the operating
tests.
1. Check that the water supply line valves are open.
2. If using a SteamerGard water treatment system, refer to the Steamer-Gard
manual and start the system. Check that all valves between the
SteamerGard and the SteamCraft 3.1 are open.
3. Open the steamer door. Check for proper installation of the drain screen,
slide racks, and door gasket assembly. Be sure the drain is not blocked.
Shut the steamer door.
4. Refer to electrical layout. Figure 2-15, and Table 2-3. Be sure the main
power switch is in the off position. Verify installation of proper size fuses
or breakers.
Printed 12/90
Summary of Contents for steamcraft 21-CET-8
Page 9: ......
Page 53: ...Model 21 CET 8 Service Manual Page 45 Printed 12 90 ...
Page 104: ...Model 21 CET 8 Service Manual Page 97 Printed 12 90 ...
Page 109: ...Figure 6 1 Major Component Groups Printed 12 90 ...
Page 112: ...Page 106 21 CET 8 Service Manual Figure 6 3 Steamer Compartment Group Printed 12 90 ...
Page 114: ...Figure 6 4 Compartment Door And Hinge Assemblies Printed 12 90 ...
Page 120: ...Page 114 21 CET 8 Service Manual Figure 6 7 Electrical Components Assembly Printed 12 90 ...
Page 122: ...Figure 6 8 Steam Generator Assembly Printed 12 90 ...
Page 124: ...Figure 6 0 Heater Assembly Printed 12 90 ...
Page 130: ...Figure 6 11 Water Inlet System Printed 12 90 ...
Page 132: ...Figure 6 12 Condenser And Drainage Systems Printed 12 90 ...
Page 134: ...Figure 6 13 Equipment Stand Printed 12 90 ...
Page 136: ...Figure 6 14 SteamCraft 3 1 Wiring Diagram Electronic Time Printed 12 90 ...
Page 137: ...Figure 6 15 SteamCraft 3 1 Schematic Diagram Electronic Timer Printed 12 90 ...
Page 138: ...Figure 6 16 SteamCraft 3 1 Wiring Diagram Mechanical Timer Printed 12 90 ...
Page 139: ...Figure 6 17 SteamCraft 3 1 Schematic Diagram Mechanical Timer Printed 12 90 ...