INSTALLATION
1.
Visual
Examine unit for scratches, dents, or other defects.
2.
Visual
Check flanged feet all have bolts holding them.
3.
General
Check all accessible wiring, mechanical and plumbing connections by hand for secure,
tight and satisfactory assembly. Remove all paper.
4.
Level
Check unit has been leveled and squared correctly.
KETTLE
Although the kettle has been thoroughly tested before leaving the factory, the installer is responsible for ensuring the
proper operation of kettle once installed.
DO NOT ATTEMPT TO OPERATE THIS APPLIANCE DURING A POWER FAILURE.
KEEP APPLIANCE AND AREA FREE AND CLEAR OF COMBUSTIBLES.
1.
Before turning the kettle on, read the vacuum/pressure gauge. The gauge's needle should be in the green zone.
If the needle is in the "VENT AIR" zone, follow air venting procedure.
2.
Supply power to the kettle by placing the fused disconnect switch to the "ON" position.
3.
Turn on main gas supply to unit. Open the kettle's shut-off valve (located at back of console).
4.
Turn the temperature control knob to "1`" (Min.). The green LED light should remain lit, indicating the burner is lit, until the
set temperature is reached. Then the green light will cycle on and off, indicating the burner is cycling on and off to
maintain temperature.
5.
Tilt the kettle forward. After a few seconds the red "LOW WATER" light should be lit when the kettle is in a tilted
position. This light indicates that the burner has automatically been shut off by the kettle's safety circuit. This is a
normal condition when the kettle is in a tilted position.
6.
Raise the kettle to the upright position. The red "LOW WATER" light should go out when the kettle is upright.
7.
Turn the temperature control knob to "10" (Max.) and allow the kettle to preheat. The green light should remain on
until the set temperature is reached. Then the green light will cycle ON and OFF, indicating the burner is cycling
ON and OFF to maintain temperature
MIXER
1.
Raise Bridge
If bridge does not raise then check motor rotation. Bridge should not raise until speed control
is turned to minimum and then adjusted back up.
2.
Swing Bridge
Bridge when fully raised should swing without hitting any object, i.e. control housing,
kettle lip. Check that hydraulic hoses are not being pinched by stops on swivel assembly.
3.
Tilt Kettle
Kettle tilts smoothly both down and back up. If power tilt, check that micro switches are
adjusted properly (kettle is level in upright position and drains fully when tilted) and are
not being crushed by gear.
4.
Lower Bridge
Raise bridge. Switch to mix. Turn speed control to zero to reset micro switch then set
speed control to number four. Check that unit does not begin to mix until bridge has
lowered part way into the kettle. Check that mixer bridge pin lowers into pin hole correctly
5.
Speed Control -
Main agitator arm not rotating when set at "0" but will start to move slowly on
Main
"1" . Speed control makes positive contact with micro switch.
6.
Speed Control -
Set main speed control to five. Adjust secondary control from
Secondary
minimum to maximum. Look for considerable speed variance.
7.
Water Faucets
Turn on hot water faucet. Turn off and check for leaks in piping and drips from
faucet spout. Repeat above with cold water faucet.
8.
Product Discharge
Add water to kettle. Check for leaks from valve. Open and close valve a few times
Valve
and check for leaks again.
QUALITY ASSURANCE CHECKS