Date
Time
Verified
By
Activity
Task No.
Grounding evaluation
• Circuit breaker size
• CO ground (AC powered systems)
4
Cable and interface equipment evaluation
• Cable type
• Connector type
• Cable distance limitations
• Interface equipment (transceivers)
• Cable bundling sizes
5
EMI evaluation
• Distance limitations for signaling
• Site wiring
• RFI levels
6
1
Verify that each power supply installed in the chassis has a dedicated AC source circuit.
2
Refer to the power supply'VA rating as a sizing criteria in determining the output required by the UPS.
The power supply kVA rating value is listed in the specifications table for each power supply in Appendix
A (power supply specifications).