6.4.2
Installation of swing-out rotors
• Push the loaded rotor onto the rotor shaft until it reaches the stop.
• Follow the safety instructions and hazard warnings (see chapter 3 -
Pos : 138 /010 Univ ers almodul e/ Leerz eile @ 0\mod_1202116244500_0.docx @ 114 @ @ 1
Pos : 139 /200 Chris t/370 R VC-BA (ST ANDARDM ODU LE)/ 060 Betrieb/ 060-0040- 0030 Ei nsetz en von Z ubehör (außer 2- 18) @ 25\mod_1404985118739_68. doc x @ 187191 @ 3 @ 1
→
6.4.3
Installation of accessories
• Only use inserts that are suitable for the rotor (see chapter 11.2 - "Rotor
• In swing-out rotors, all places of a rotor must be loaded with buckets..
• Always load the opposite inserts of the rotors with the same accessories
and fill to avoid imbalance.
Evaporation with different tube sizes
Working with different tube sizes is possible. In this case, however, it is
very important that the inserts are installed symmetrically (see figure).
Fig. 14: Permissible loading of the swing-out rotor with different tube sizes