PG80MSU: Installation, Start-up, Operating and Service and Maintenance Instructions

Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.

9

A89014

Fig. 10 – Leveling Legs

2. For each leg, install nut on bolt and then install bolt and nut in hole.

(Install flat washer if desired.)

3. Install another nut on other side of furnace base. (Install flat washer

if desired.)

4. Adjust outside nut to provide desired height, and tighten inside nut

to secure arrangement. 

5. Reinstall bottom closure panel if removed.

Downflow Installation

NOTE: 

For downflow applications, this furnace is approved for use on

combustible flooring when any one of the following 3 accessories are

used:

• Manufacturer’s approved downflow combustible floor subbase

• Manufacturer’s approved cased evaporator coil

• Manufacturer’s approved evaporator coil casing

1. Determine application being installed from 

Table 4

.

2. Construct hole in floor per 

Table 4

 and 

Fig. 11

.

3. Construct plenum to dimensions specified in 

Table 4

 and 

Fig. 11

.

4. If  downflow  subbase  is  used,  install  as  shown  in 

Fig. 12

.  If

manufacturer’s cased evaporator coil or coil casing is used, install

as shown in 

Fig. 13

.

NOTE: 

It  is  required  that  the  perforated  supply-air  duct  flanges  be

completely  folded  over  or  removed  from  furnace  when  installing  the

furnace  on  a  factory-supplied  cased  coil  or  coil  box.  To  remove  the

supply-air  duct  flange,  use  wide  duct  pliers  or  hand  seamers  to  bend

flange back and forth until it breaks off. Be careful of sharp edges, see

Fig. 17

.

Bottom Return Air Inlet

These furnaces are shipped with bottom closure panel installed in bottom

return-air opening. Remove and discard this panel when bottom return

air is used. To remove bottom closure panel, perform the following:

1. Tilt or raise furnace and remove two screws holding bottom filler

panel, see 

Fig. 9

. 

2. Rotate bottom filler panel downward to release holding tabs.
3. Remove bottom closure panel.
4. Reinstall bottom filler panel and screws

A96283

Fig. 11 – Floor and Plenum Opening Dimensions

A96285

Fig. 12 – Furnace, Plenum, and Subbase Installed

 on a Combustible Floor 

A08556

Fig. 13 – Furnace, Plenum, and Coil Assembly or

Coil Box Installed on a Combustible Floor

WARNING

!

FIRE AND PROPERTY HAZARD

Failure  to  follow  this  warning  could  result  in  equipment  damage,

personal injury, or property damage.

When furnace is installed in a downflow application, make sure water

lines and other sources of water cannot drip or fail in such a way that

water  can  collect  on  the  blower  motor,  wiring,  and  furnace  control

board.

Summary of Contents for PG80MSU

Page 1: ...NFORMATION GUIDE 40 MODEL NOMENCLATURE 40 To learn more about this appliance and installation via a mobile device go to https www payne com NFC or use the QR code below To access airflow tables or tro...

Page 2: ...se carbon monoxide poisoning explosion fire electrical shock or other conditions which may cause personal injury or property damage Consult a qualified service agency local gas supplier or your distri...

Page 3: ...ply ducts carry air circulated by the furnace to areas outside the space containing the furnace the return air shall also be handled by duct s sealed to the furnace casing and terminating outside the...

Page 4: ...db Failure to follow these return air temperature limits may affect reliability of heat exchangers motors and controls see Fig 4 For accessory installation details refer to the applicable instruction...

Page 5: ...city firmly touch a clean unpainted metal surface of the furnace again before touching control or wires 5 Use this procedure for installed and uninstalled ungrounded furnaces 6 Before removing a new c...

Page 6: ...ut rating for all gas appliances installed in the space Spaces having less than 50 cubic feet per 1 000 BTUh require the OUTDOOR COMBUSTION AIR METHOD Spaces having at least 50 cubic feet per 1 000 BT...

Page 7: ...ss volume than 50 cubic feet per 1 000 BTUh of the maximum input ratings for all gas appliances installed in the space and 2 The air infiltration rate is not known to be less than 0 40 air changes per...

Page 8: ...ings with unusually tight construction additional air MUST be provided using the methods described in the Outdoor Combustion Air Method section Unusually tight construction is defined as construction...

Page 9: ...own in Fig 13 NOTE It is required that the perforated supply air duct flanges be completely folded over or removed from furnace when installing the furnace on a factory supplied cased coil or coil box...

Page 10: ...Protection Provide a minimum 17 3 4 in x 22 in 451 mm x 559 mm piece of sheet metal for flame roll out protection in front of burner area for furnaces closer than 12 inches 305 mm above the combustibl...

Page 11: ...n a 1 in 25 mm clearance from combustible materials to supply air ductwork for a distance of 36 in 914 mm horizontally from the furnace See NFPA 90B or local code for further requirements Ductwork Aco...

Page 12: ...GC Installations must be made in accordance with all authorities having jurisdiction If possible the gas supply line should be a separate line running directly from meter to furnace NOTE In the state...

Page 13: ...and downstream of manual equipment shutoff valve A02035 Fig 22 Typical Gas Pipe Arrangement Piping should be pressure and leak tested in accordance with NFGC in the United States local and national pl...

Page 14: ...in Step 1 5 Route J Box wires within furnace away from sharp edges rotating parts and hot surfaces WARNING ELECTRICAL SHOCK AND FIRE HAZARD Failure to follow this warning could result in personal inju...

Page 15: ...ket BX Cable Installation in Furnace J Box 1 Remove cover from J Box 2 Route BX cable into 7 8 inch diameter hole in J Box 3 Secure BX cable to J Box bracket with connectors approved for the type of c...

Page 16: ...sted or draft hood equipped appliances in accordance with the NFGC the local building codes and furnace and vent manufacturers instructions The following information and warning must be considered in...

Page 17: ...in operation Seal any unused openings in venting system Inspect the venting system for proper size and horizontal pitch as required in the current edition of National Fuel Gas Code ANSI Z223 1 NFPA 5...

Page 18: ...condensation and corrosion in the venting system Do not use vent dampers on appliances common vented with this furnace Additional Venting Requirements A 4 101 mm round vent elbow is supplied with the...

Page 19: ...t connector is required refer to Note 1 above 3 Side outlet vent for upflow and downflow installations must use Type B vent immediately after exiting the furnace except when factory authorized Downflo...

Page 20: ...0 935 875 815 750 690 620 570 520 470 6 1050 995 935 880 820 755 700 645 595 550 7 1130 1075 1020 970 915 855 800 745 690 645 8 1200 1150 1100 1050 1000 945 890 840 785 735 9 1285 1240 1190 1145 1095...

Page 21: ...315 175 3 1035 935 830 745 640 550 460 365 235 140 4 1095 1000 900 815 725 630 545 455 360 240 5 1205 1125 1035 945 870 780 695 620 540 455 6 1290 1210 1125 1040 965 890 805 725 645 570 7 1385 1310 1...

Page 22: ...ct Super Plug available from distributor replacement component for the control board to copy the correct model program onto the new board Further details and instructions for these programming methods...

Page 23: ...Service and Maintenance Instructions Manufacturer reserves the right to change at any time specifications and designs without notice and without obligations 23 A221015 Fig 34 3 Digit Display Flow Char...

Page 24: ...to the gas valve if a flame rollout or overheating condition occurs in the gas control area DO NOT bypass the switches Correct inadequate combustion air supply problem before resetting the switches CA...

Page 25: ...e unit rating plate For installation above 2 000 ft 610 M multiply the input on the rating plate by the derate multiplier in Table 14 for the correct input rate A180238 Fig 37 Orifice Hole WARNING FIR...

Page 26: ...door switch f Set thermostat to call for heat g Remove regulator seal cap and turn regulator adjusting screw counterclockwise out to decrease input rate of clockwise in to increase input rate h Instal...

Page 27: ...2 6 2 7 2 8 2 9 850 2 4 2 5 2 6 2 7 to 875 2 3 2 4 2 5 2 5 900 2 2 2 3 2 3 2 4 5000 925 2 1 2 1 2 2 2 3 1524 950 2 0 2 0 2 1 2 2 975 1 9 1 9 2 0 2 0 1000 1 8 1 8 1 9 1 9 U S A Only 725 3 2 3 3 3 4 3...

Page 28: ...U S A Only 725 2 9 3 0 3 1 3 1 750 2 7 2 8 2 9 3 0 5001 775 2 5 2 6 2 7 2 8 1524 800 2 4 2 4 2 5 2 6 825 2 2 2 3 2 4 2 5 to 850 2 1 2 2 2 2 2 3 875 2 0 2 0 2 1 2 2 5400 900 1 9 1 9 2 0 2 1 1646 925 1...

Page 29: ...failure If limit control does not function during this test cause must be determined and corrected a Run furnace for at least 5 minutes b Gradually block off return air with a piece of cardboard or sh...

Page 30: ...es proceed with the following NOTE NO thermostat signal may be present at control and all blower OFF delays must be completed a Leave 115 V power to furnace turned on b Remove outer access door c Remo...

Page 31: ...d dirt and grease from blower wheel and motor annually The inducer and blower motors are pre lubricated and require no additional lubrication These motors can be identified by the absence of oil ports...

Page 32: ...eel wool 0000 grade Do not use sand paper or emery cloth To reinstall igniter and flame sensor 1 Install the Hot Surface Igniter HSI and bracket with igniter gasket into burner assembly 2 Install flam...

Page 33: ...end of spring cable end opposite brush 2 Insert brush end of cable into the outlet opening of cell and slowly rotate with drill DO NOT force cable Gradually insert cable into upper pass of cell see Fi...

Page 34: ...iod the control CPU will open the gas valve relay GVR de energizing the gas valve solenoid GV The control CPU will repeat the ignition sequence for up to three more Trials for Ignition before going to...

Page 35: ...er motor BLWM operation 4 Heat pump When installed with a heat pump the furnace control automatically changes the timing sequence to avoid long blower off times during demand defrost cycles Whenever W...

Page 36: ...lation Start up Operating and Service and Maintenance Instructions Manufacturer reserves the right to change at any time specifications and designs without notice and without obligations 36 TROUBLESHO...

Page 37: ...U Installation Start up Operating and Service and Maintenance Instructions Manufacturer reserves the right to change at any time specifications and designs without notice and without obligations 37 A2...

Page 38: ...Start up Operating and Service and Maintenance Instructions Manufacturer reserves the right to change at any time specifications and designs without notice and without obligations 38 A221105 Fig 40 T...

Page 39: ...re only furnace is running Firing rate heat content btu cu ft X size of the dial cu ft rev X of rev per 60 sec rev sec X 3600 sec hr Example 1050 btu cu ft X 0 5 cu f t rev X 2 revs 60sec X 3600 sec h...

Page 40: ...ll Cell panel Inducer Group Housing assembly Transducer Inducer motor Inducer wheel TO OBTAIN INFORMATION ON PARTS Consult your installing dealer or a licensed Heating and Air Conditioning company of...