Anchoring the Machine
•
Once positioned, anchor the machine to the floor, as shown in
the diagram. Use bolts and expansion plugs or sunken tie rods
that connect through and are sized for the holes in the base of
the stand.
•
This machine requires a solid floor such as concrete at a
minimum of 4” (102mm) thick. 6” (153mm) minimum is preferred.
Tank Filling
The hydraulic oil is the primary medium for transmitting pressure and also must lubricate the
running parts of the pump.
After installation of the machine and before machine startup, bring the oil level up to 90% of
capacity. Verify that any cylinder rams are is in the retracted position to prevent overfilling of the
tank. Recheck the oil level after the first few hours of operation and again after the first full week
of operation.
A shortage of hydraulic oil can cause hydraulic system breakdown and damage to major
mechanical parts due to overheating
.
.31"
(7.87mm)
.50"
(12.7mm)
Summary of Contents for BS-330SA
Page 17: ...14 14 OVERALL DIMENSIONS...
Page 21: ...18 18 DESCRIPTION OF MACHINE PARTS A G F E H C I J B K L O P Q D M N...
Page 34: ...31 31...
Page 54: ...51 51 ELECTRICAL SCHEMATIC...
Page 55: ...52 52...
Page 56: ...53 53 Terminal Strip Connections...
Page 57: ...54 54 Switch Designation...
Page 59: ...56 56 HYDRAULIC LAYOUT...
Page 61: ...58 58 PARTS DIAGRAM...
Page 62: ...59 59...
Page 75: ...72 72 NOTES...