5 Test Procedure
©
b2 electronic
GmbH
DHV0078 b2 EN
41
Step
Procedure
(configure automatic sequence)
Example
AS7:
Frequency
(sine wave or
square wave only)
Set the frequency to as close to 0.1 Hz as possible.
•
0.1 Hz/Auto: Recommended setting that
automatically maintains the frequency as close to
0.1 Hz as possible
•
Permitted values: 0.02-0.1 Hz in 0.01 Hz
increments
AS8:
Voltage steps
Specify the number of voltage steps to be applied to
the DUT.
•
Min. voltage levels: 1 step
•
Max. voltage levels: 4 steps
AS9:
Test voltage
Specify test voltage for each step:
•
Voltage limits see
3.1 – Technical Specifications
For multiple voltage steps:
HVA automatically advances to next step.
Values are displayed in a table.
AS10:
Duration
Specify test duration for each step:
•
Min. test duration/step = 1 minute
•
Max. test duration/step = 120 minutes
For multiple voltage steps:
HVA automatically advances to next step.
Values are displayed in a table.
AS11:
Arc management
mode
Select one of the following arc management modes:
•
Trip out on arc
•
Burn on arc
AS12
(Vacuum bottle
only)
Trip current
Set the test “Trip Current”:
•
Min. = 200 µA,
•
Max. = 1000 µA
New Auto Test Seq.
1.0kV Cable XPLE
Maintenance / Sine
Frequency for Test?
0.1Hz/ Auto
CANCEL PREV
NEXT
New Auto Test Seq.
0.1kV Cable XPLE
Maintenance/Sine0.1Hz
How many Steps?
1 Step
CANCEL PREV
NEXT
New Auto Test Seq.
1.0 Cable XPLE
Maintenance/Sine0.1Hz
Test Voltage: 1.0kVrms
Step 1
Test Voltage
1.0kVrms
CANCEL PREV
NEXT
New Auto Test Seq.
60.0 kV Cable XPLE
Maintenance/Sine0.1Hz
Test Voltage: 1.0kVrms
Step 1
Duration
15 min
CANCEL PREV
NEXT
New Auto Test Seq.
1.0kV Cable XPLE
Maintenance/Sine0.1Hz
Test Voltage: 1.0kVrms
Duration: 15 min
Current Limit?
Trip out on Arc
CANCEL PREV
NEXT
New Auto Test Seq.
60.0kV Vacuum Bottle
Maintenance
Test Voltage 1.0kV
Duration: 1min 0sec
Trip Current?
200µA
CANCEL PREV
NEXT
Summary of Contents for HVA120
Page 2: ...1 Introduction 2 DHV0078 b2 EN b2 electronic GmbH...
Page 11: ...2 Safety b2 electronic GmbH DHV0078 b2 EN 11...
Page 33: ...5 Test Procedure b2 electronic GmbH DHV0078 b2 EN 33 Connection diagram vacuum bottle test...
Page 47: ...5 Test Procedure b2 electronic GmbH DHV0078 b2 EN 47 5 5 Discharge Status...
Page 63: ...11 Declaration of Conformity b2 electronic GmbH DHV0078 b2 EN 63 HVA30 5...
Page 64: ...11 Declaration of Conformity 64 DHV0078 b2 EN b2 electronic GmbH HVA30 7 HVA40 5 HVA54 3...
Page 65: ...11 Declaration of Conformity b2 electronic GmbH DHV0078 b2 EN 65 HVA54 5...
Page 66: ...11 Declaration of Conformity 66 DHV0078 b2 EN b2 electronic GmbH HVA60...
Page 67: ...11 Declaration of Conformity b2 electronic GmbH DHV0078 b2 EN 67 HVA68 2...
Page 68: ...11 Declaration of Conformity 68 DHV0078 b2 EN b2 electronic GmbH HVA90 HVA94...
Page 69: ...11 Declaration of Conformity b2 electronic GmbH DHV0078 b2 EN 69 HVA120...