Operation and shut down of this instrument
Azbil Corporation
3-2
Model: MVC10A/10F - Multivariable Air Flow Meter
3-1:
Startup
Activating this instrument
Procedure
Use the following procedure for starting up this instrument:
Step
Procedure
1
Ensure that this instrument is correctly fitted to the piping.
2
Ensure that the wiring of the detector and converter for this instrument have been
securely conducted.
3
Fill this instrument with the fluid to be measured and let it stay still for a while.
4
Ensure that no leakage is found from the flanges on which this instrument is fitted.
5
Energize the converter for this instrument.
6
Ensure that LCD display is activated.
Summary of Contents for MVC10A