Chapter 3: Configuration and commissioning
2X Series Installation Manual
93
Per zone (sounder, fire routing, fire protection, or program)
Select the Per zone option to activate output groups with different delays
(including no activation) depending on which zone generated the alarm.
All outputs assigned to the output group activate depending on alarms in the fire
network, in the local range of zones of the panel, and with different delays.
For example, select this option to activate output group number 5 (sounder, fire
routing, fire protection, or program) with a delay of 10 seconds for a detector
alarm in zone 1 and with a delay of 2 minutes for a detector alarm in zone 5.
To configure per zone delay options:
1. Select Field setup from the Main menu, and then select Activation
configuration.
2. Select Per zone.
3. Select the zone, and then select the output group whose delay you want to
configure for the selected zone.
The corresponding output group configuration options for the selected zone
are displayed on the screen.
4. Select Active, and then select YES or NO to define output group activation for
the zone.
5. Enter the required delay in minutes and seconds.
The maximum delay value for sounder, fire routing, and fire protection output
groups is 10 minutes. The maximum delay value for program output groups is
16 minutes and 40 seconds.
6. If required, enter a warning delay (in minutes and seconds) for sounder output
groups in applications using warning tones (second stage sounders).
A warning delay is only observed if the corresponding warning time is also
configured (see “Warning time” on page 97 for more information on this
option). The maximum warning delay value is 10 minutes.
7. Press F4 (Enter), and then press F1 (Back).
8. Press F1 (Save), F3 (Apply), F4 (Discard), or F2 (Exit).
Remember to apply saved settings from the Main menu.
Outputs assigned to an output group (for example, output group 5 SND) are
activated depending on alarms in the fire network and with the corresponding
delays.
For example, if we have a one-loop control panel with the initial zone set to 100
and we want to configure sounder output group number 5, the following can be
configured with this option:
• No activation for zones 100 to 119
• Activation with a 10 second delay for zones 120 to 139
Summary of Contents for 2X Series
Page 1: ...2X Series Installation Manual P N 501 405003 1 31 REV 03 10 ISS 07NOV13 ...
Page 6: ...iv 2X Series Installation Manual ...
Page 20: ...Chapter 1 Introduction 14 2X Series Installation Manual ...
Page 110: ...Chapter 3 Configuration and commissioning 104 2X Series Installation Manual ...
Page 140: ......