Allied Construction Products, LLC www.alliedcp.com
SOMM577202_14mar
47
14.0 Technical Information – [cont’d]
Fig 14-4 Fastener Location
Fig. 14-5 Each Flat = 60
Rotation. Fastener
Tightening Sequence
Table 14.2 A - Side Rod
MPORTANT
Model
A- Side Rod Torque
Apply Moly-Paste 676927 to threads at assembly.
Follow sequence (Fig. 14-5) to ensure each tie rod is evenly
loaded.
Follow progressive tightening* steps 1-4.
*Progressive tightening means the nut will be turned a little at a
time. Never exceed 1 full turn without turning the other 3 nuts.
HR270,
HR290
Refer to Table 14.3
Table 14.3 A - Side Rod Torque Ft-Lbs [N.m]
Model
Step 1
Step 2
Step 3
Final Torque
Step 4
HR270
110
[150]
220
[300]
330
[450]
440
[600]
HR290
165
[220]
330
[450]
500
[675]
660
[900]
Table 14.4 D - Mounting Bracket
Fasteners Ft-Lbs [N.m]
Model
D – M16
HR270,
HR290
130
[175]
Fig 14-6 Mounting Bracket