6.
Verify Inter-shelf Communication
If the installation consists of multiple shelves which have been wired together via
the RS-485 management bus, perform the procedure outlined in DLP-725 to verify
that the shelves are properly connected and communicating.
7.
Verify External Modem Connection
If an external modem connection has been made, place a call from a remote
modem into the Total Access 3000/3010 modem to verify that the modem is
properly connected and functioning. Once the call is connected, logon to the
system and verify that the menus are properly displayed. When menu verification
is complete, logout of the shelf and disconnect the call.
8.
Verify OSS Connections
If one of the shelves is connected to a remote OSS via TL1 over X.25, use the
procedure in DLP-726 to verify that the connection to the OSS is functioning
properly. Repeat DLP-726 for each OSS connection.
9.
Verify IP LAN Connection
If the shelf is connected via the 10BaseT port to a network, use the procedure in
DLP-727 to verify that the network connection is properly configured and
working.
1.2.1
Followup Procedures
Once this procedure is complete, the Total Access 3000/3010 shelves should be ready
for installation of multiplexer modules and access modules. If a multiplexer module is
to be installed in any of the shelves, find the Installation and Turnup Procedure (NTP)
for that module and proceed with the installation. Once any multiplexer modules have
been installed and tested, use the installation instructions for the access modules to
install them as required.