Figure 19: Converter, 2-connector
Figures 1 and 2
3. Remove the fuse resistors by pulling away from the converter.
a. For converters with 1 connector, always replace both fuse resistors at the same time.
b. For converters with 2 connectors, always replace both fuse resistors related to the A/B channel that needs to be reset.
Make sure you replace all 4 fuse resistors, if both A and B channel needs a reset.
4. Dispose the old fuse resistor.
5. Place the legs of the new fuse resistors in the sockets.
6. Assemble the light fixture and perform a functional test.
5.3.11 Checking the Light Fixture for Water-tightness
Tools to be used:
•
Flat head screwdriver
•
For water tight testing, pressure test fitting tool to be used : 44A6104/A
Execute the following procedure to test for leaks:
1. Remove the Pressure-relief Screw.
Refer to the image below.
Figure 20: Pressure-relief screw removal
2. Screw the pressure test fitting to the Pressure-relief Port.
UM-5056, Rev. 1.0.17, 2022/12/08
39
Copyright
©
ADB Safegate, All Rights Reserved