Copyright © Acronis, Inc., 2000-2010
165
From:
09/20/2009
.
To:
not set
.
Second daily schedule
1.
Every:
3
day(s).
2.
Every:
2
hour(s).
From:
03:00:00 PM
Until:
07:00:00 PM
.
3.
Effective:
From:
09/20/2009
.
To:
not set
.
5.2
Weekly schedule
Weekly schedule is effective in Windows and Linux operating systems.
To specify a weekly schedule
In the
Schedule
area, select the appropriate parameter as follows:
Every: <...> week(s) on: <...>
Specify a certain number of weeks and the days of the week you want the
task to be run. For example, with the Every
2
week(s) on
Mon
setting, the task
will be performed on Monday of every other week.
In the
During the day execute the task...
area, select one of the following:
Once at: <...>
Set up the time at which the task will be run once.
Every: <...>
From: <...> Until: <...>
Set up how many times the task will be run during the specified time interval.
For example, setting the task frequency to Every
1
hour From
10:00:00 AM
until
10:00:00 PM
allows the task to be run 12 times from 10 AM to 10 PM
during one day.
In the
Effective...
area, set the following settings:
From: <...>
Set up a date when this schedule will be enabled (an effective date). If this
check box is cleared, the task will be started on the nearest day and time you
have specified above.
To: <...>
Set up a date when this schedule will be disabled. If this check box is cleared,
the task will be run for an indefinite number of weeks.
Advanced scheduling settings (p. 171) are available only for machines registered on Acronis Backup &
Recovery 10 Management Server. To specify these settings, click
Change
in the
Advanced settings
area.
All the settings you made are displayed in the
Result
field at the bottom of the window.
Examples
"One day in the week" schedule
Run the task every Friday at 10PM, starting from a certain date (say 05/14/2009) and ending after six
months.
The schedule's parameters are thus set up as follows.
1.
Every:
1
week(s) on:
Fri
.
2.
Once at:
10:00:00 PM
.