pREpARINg fOR INSTALLATION
15
4. When the foundation block has been brought into position, adjusted with a spirit
level and the necessary power supply cables have been inserted, you can refill the
excavated pit and compact the fill.
Foundations laid by the operator
Alternatively, the operator may construct a foundation allowing for a similarly secure
and durable attachment of the charging pole. In this case, the specifications listed on
page 33 must be followed.
Proceed as follows to construct a foundation for installing the
eMC2
:
1. After selecting a suitable installation site (see page 13), excavate a sufficiently
large pit. Select dimensions ensuring stability in all directions and the secure instal-
lation of the
eMC2
using one of the separately available plinths.
2. Construct the formwork (e.g. lost formwork).
3. Place an empty tube inside and insert the non-live power supply. If possible, fix the
tube into place in such a way that the power supply can be easily inserted into the
charging pole via the separately available plinth.
4. Seal the openings of the tube so that no moisture can enter.
5. Pour the foundation using grade C30/37 concrete.
6. Allow the concrete to cure completely before beginning with the installation of the
charging pole.
CAUTION!
In case of concrete foundations poured on site, calculations, design
and construction are the sole responsibility of the operator or the
company contracted by the operator to carry out the installation.
Summary of Contents for eMC2