2
100
Ze nit h Z TG S e r i e s AT S ,
O PER AT I O N , M A I N T EN A N C E , A N D I N S TA L L AT I O N G U I D E
—
9.1 Basic Tools for Installation and Maintenance
Tool
Task
1/4" to 1/2" Allen head socket driver
Power cable connection
Torque wrench
Torqueing of the lugs and other hardware as required.
Range of device to be 50 - 500 in-lbs (5-57 N-m)
Torque screwdriver
Torqueing of control wire terminations, auxiliary contact
input terminals. 5 - 25 in-lbs (0.5 - 2.8 N-m)
Wire cutters/wire crimpers
Auxiliary contacts wire installation, Options installation
Voltmeter
Trouble shooting tool for measuring incoming voltage,
frequency, continuity and control signal transmission.
Controller default password 00001
Changing parameters within the controller
—
Table 9.1 Required tools for common installation and maintenace tasks
—
9.2 Equipment Inspection and Storage
Warning
When performing a hi-pot or dielectric test on
the power section of the ATS panel, DISCON-
NECT the complete electronics, controller,
and mechanism section of the ATS from the
power section to avoid potential damage to
the electronics.
Once you have received the transfer
switch, inspect it for any damage. This in-
cludes damage to the enclosure, power
panel, control panel and wiring harness. If
any damage is found or suspected, file a
claim as soon as possible with the carrier
and notify the nearest ABB Zenith
representative.
Before installation, if it is necessary, store
the transfer switch in a clean dry place,
protected from dirt and water. Provide
ample air circulation and heat, if neces-
sary, to prevent condensation.
See table 7.1 for recommended storage
and ambient operating temperatures.
Summary of Contents for Zenith ZTG 30
Page 2: ......
Page 6: ...6 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE 1 ...
Page 10: ...10 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE 1 ...
Page 52: ...52 1 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...
Page 91: ...91 1 Fig 7 3 ZTGD delayed transition circuit diagram ...
Page 93: ...93 1 Figure A Figure B ...
Page 94: ...94 1 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE Figure C ...
Page 96: ...2 96 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...
Page 108: ...2 108 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...
Page 114: ...2 114 Zenith ZTG Series ATS OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...