104
Four parameter setting groups (GRP)
Chapter 13
Verifying settings by secondary
injection
11
Four parameter setting groups (GRP)
11.1
Verifying the settings
Prepare the terminal for verification of settings as outlined in
section 2 "Preparing for test"
in
this chapter.
Procedure
1.
Check the configuration of binary inputs that control the selection of
active setting group.
2.
Browse the ‘ActiveGroup’ menu to achieve information about the ac-
tive setting group.
The ActiveGroup menu is located in the local HMI under:
ServiceReport/ActiveGroup
3.
Connect the appropriate dc voltage to the corresponding binary in-
put of the terminal and observe the information presented on the HMI
display.
The displayed information must always correspond to the activated input.
4.
Check that corresponding output indicates the active group.
5.
Continue to test another function or complete the test by setting the
test mode to off.
Summary of Contents for REB 551-C3*2.5
Page 9: ...Contents ...
Page 21: ...12 Introduction to the installation and commissioning manual Chapter 1 Introduction ...
Page 27: ...18 Note signs Chapter 2 Safety information ...
Page 53: ...44 Installing the 56 64 kbit data communication cables Chapter 5 Installing the terminal ...
Page 59: ...50 Checking the binary I O circuits Chapter 6 Checking the external circuitry ...
Page 147: ...138 Repair support Chapter 16 Fault tracing and repair ...