8 - Maintenance

M

easuring the insulation resistance of photovoltaic generator

To measure the insulation resistance of the PV generator compared to 
ground 

, the two poles of the PV generator must be short-circuited 

(using a suitably sized switch).

+

_

IG

Once the short-circuit has been made, measure the insulation resistance 
(Riso) using a megohmmeter positioned between the two shorted poles 
and ground (of the inverter). 

Mega

Inverter

IG

+

_

-TL MODELS (transformerless). 

If the measured insulation resistance 

(Riso) is less than 1Mohm the inverter does not connect to the grid due 
to a low insulation of photovoltaic generator respect to ground. 

-I MODELS (with high frequency transformer). 

If the measured insu-

lation resistance ( Riso in case of input poles floating respect to ground 

or QF=1 if the one of input poles is grounded) is less than 0.2Mohm the 
inverter does not connect to the grid due to a low insulation of photovol-
taic generator respect to ground. 

The insulation resistance is affected by the environmental conditions the PV generator is in 
(E.g.: photovoltaic module wet from dump or rain), and therefore the measurement must be 
made immediately after the anomaly 

Скачано

 

с

 

сайта

 

интернет

 

магазина

 https://axiomplus.com.ua/

Summary of Contents for REACT-3.6-TL

Page 1: ...ABB solar inverters Product manual REACT 3 6 4 6 TL from 3 6 to 4 6 kW Скачано с сайта интернет магазина https axiomplus com ua ...

Page 2: ...n and maintenance of the equipment Operators are required to read this manual and scrupulously follow the instructions given in it since ABB cannot be held responsible for damage caused to people and or property or to the equipment if the conditions described below are not observed Скачано с сайта интернет магазина https axiomplus com ua ...

Page 3: ...ormation 2 Characteristics 3 Safety and accident prevention 4 Lifting and transport 5 Installation 6 Instruments 7 Operation 8 Maintenance REACT 3 6_4 6 TL Product Manual EN Rev B M000025BG EFFECTIVE 28 04 2016 Copyright 2016 ABB All Rights Reserved Скачано с сайта интернет магазина https axiomplus com ua ...

Page 4: ...rning either hardware or software shall result in the immediate cancellation of the warranty The customer is fully responsible for any changes made to the system Given the countless array of system configurations and installation environments possible it is essential to check the following adequate spaces suitable for housing the equipment airborne noise produced based on the environment possible ...

Page 5: ...entification of the equipment and manufacturer 21 Characteristics and technical data 22 Tightening torques 25 Overall dimensions REACT 3 6 4 6 TL 26 Overall dimensions REACT MTR 1PH 27 Overall dimensions REACT MTR 3PH 27 Dimensions main bracket REACT 3 6 4 6 TL 28 Dimensions additional bracket REACT BATT AP1 29 Efficiency curves 30 Power limitation Power Derating 31 Power reduction due to environm...

Page 6: ...omponents supplied 56 Installation 58 General conditions 58 Environmental checks 59 Installation position 61 Wall installation of the REACT system 62 Wall installation of the REACT UNO alone 66 Connection of the energy meter REACT MTR 70 Connection of the REACT MTR 1PH mono phase 70 Connection and configuration of the REACT MTR 3PH three phase 72 Preliminary operations for connection of the PV gen...

Page 7: ...e Relay connection ALARM 99 Connection to load management system Load Manager Box 100 Instruments 101 General conditions 101 Display keyboard and status LED 102 Description of symbols and display fields 102 Description of the keyboard and status LEDs 106 Operation 107 General conditions 107 Monitoring and data transmission 108 User interface 108 Measurement tolerance 108 Commissioning 109 Updating...

Page 8: ...o change the grid standard 168 Verification of ground leakage 169 Behaviour of a system without leakage 169 Behaviour of a system with leakage 170 Measuring the insulation resistance of photovoltaic generator 171 Storage and dismantling 172 Storage of the equipment or prolonged stop 172 Dismantling decommissioning and disposal 172 Further information 173 Contact us 174 Скачано с сайта интернет маг...

Page 9: ...n the right 14 REACT BATT AP1 44 termination switch for internal communication line 15 VSN300 Wi Fi Logger Card 45 connector for internal communication line cable from unit on the left 16 expansion board connector 46 input connectors MPPT1 17 RJ45 connectors for serial RS485 PC 47 input connectors MPPT2 18 termination switch for PC RS485 line 48 AC cable gland 19 termination switch for METER RS485...

Page 10: ...troduction and general information Graphical representation of references REACT 3 6 4 6 TL 01 02 03 04 05 06 07 08 09 10 51 14 13 12 11 46 07 47 08 48 02 49 50 52 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 11: ... 6 TL LOAD MANAGER BOX 8 7 D 5 6 C 3 4 B 1 2 A J1 5 1 6 2 7 3 8 4 LOAD MANAGER BOX 8 7 D 5 6 C 3 4 B 1 2 A J1 5 1 6 2 7 3 8 4 03 04 05 06 10 09 07 53 15 16 17 18 19 20 21 22 23 24 25 26 08 27 28 33 34 31 32 30 29 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 12: ...Y DC POWER D1 D2 D3 OFF J2 J1 J7 PE 120 Ω ON BATTERY ADDRESS SELECTOR DC POWER LINK J6 J5 BATT COMM BUS BATT COMM BUS 3 J 4 J M O C O I Y R E T T A B I T L U M K N I L M O C O I MULTI BATTERY DC POWER D1 D2 D3 OFF J2 J1 J7 PE 120 Ω ON BATTERY ADDRESS SELECTOR DC POWER LINK 14 11 12 13 35 36 45 44 43 42 41 40 39 38 37 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 13: ...troduction and general information REACT MTR 1PH REACT MTR 1PH S U T A T S E R U S A E M INPUT 110 230 V 50 60 Hz 10 mA max 57 56 55 54 REACT MTR 3PH 59 59 60 58 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 14: ...the use and routine maintenance of the equipment Operator and maintenance personnel skills prerequisites Personnel in charge of using and maintaining the equipment must be skilled for the described tasks and must reliably demonstrate their capacity to correctly interpret what is described in the manual For safety reasons only a qualified electrician who has received training and or demonstrated sk...

Page 15: ...rts at high temperatures risk of burns Risk of explosion Risk of injury due to the weight of the equipment Take care during lifting and transport Indicates that the area in question must not be accessed or that the operation described must not be carried out Keep out of the reach of children Indicates that smoking and the use of naked flames is prohibited Indicates that it is mandatory to carry ou...

Page 16: ...on the identification label DC Direct Current AC Alternate current With insulation transformer Without insulation transformer Positive pole of the input voltage DC Negative pole of the input voltage DC Indicates the centre of gravity of the equipment Indicates the requirement to wear acoustic protection devices in order to prevent damage to hearing Скачано с сайта интернет магазина https axiomplus...

Page 17: ...ures energy at the connection point to the grid and communicates with REACT UNO in order to maximise energy self sufficiency by managing the storage system Limits in field of use The REACT system can be used only with photovoltaic modules which do not require the grounding of one of the input poles unless accessories are installed which are compatible with the inverter and enable this operation to...

Page 18: ...nt unless expressly provided for Modify operating parameters that are not accessible to the operator and or parts of the equipment to vary its performance or change its insulation Clean the equipment with corrosive products that may attack parts or generate electrostatic charges Use or install the appliance or parts of it without having read and understood the contents of the user and maintenance ...

Page 19: ...nt identification The customer Installer takes full responsibility if when reading this manual the chronological order of its presentation provided is not observed All information is provided considering occasional inclusion of information in previous chapters In certain cases there may be a need to separately document software functionality or attach supplementary documentation to this manual whi...

Page 20: ...grid Battery unit REACT BATT AP1 average battery capacity 2kWh In the system up to three REACT BATT AP1s can be used maximum capacity of the system 3x2kWh 6kWh Energy meter REACT MTR 1PH energy meter for single phase line REACT MTR 3PH energy meter for three phase line The choice of the components for the system must be made by a qualified technician who knows about the installation conditions the...

Page 21: ...LAR www abb com solar BACKUP OUTPUT 2 230 V 1Ø 50 Hz 3000 VA 13 A Regulatory Label of REACT UNO 3 6 TL 1 Over Under excited Adj cosφ 0 1 1 1 2 Optionally available PROTECTIVE EARTHING REQUIRED All material used and finished product must meet the requirements of the current RoHS recti i ve 2002 95 EC Title Issued Modified D D esign approved Elec Eng approved Mfg approved Size Scale Dim in mm Sheet ...

Page 22: ...varistor Yes Insulation check Complying with the local regulations Characteristics of DC disconnect switch for each MPPT 25 A 660 V Battery charger Maximum charge power with minimum of 3 x REACT BATT AP1 3000 W Maximum discharge power with minimum of 2 x REACT BATT AP1 3000 W Output AC grid connection type Single phase Nominal AC power Pacr cosφ 0 9 1 over under excited 3600 W 4600 W Maximum AC po...

Page 23: ...s channel CEI 0 21 DIN V VDE V 0126 1 1 VDE AR N 4105 G83 2 G59 3 VFR2014 4777 2 2015 Other characteristics Load management Yes through load manager box AC back up output off grid Yes automatic or manual restart in the case of no grid Grid support Yes where required by the regulations 1 The output voltage range may vary according to the grid standard of the country of installation 2 The output fre...

Page 24: ...ty and EMC EN62109 1 EN62109 2 compliant with the applicable requirements of EN60950 1 EN61000 6 2 EN61000 6 3 UN38 3 UN3480 Meter REACT MTR 1PH REACT MTR 3PH AC Meter Obligatory for optimal energy management Measurements P Q A V I Measurement accuracy resolution 1 1 Maximum current 30 A 65 A Number of AC phases 1 3 Nominal voltage voltage range 230 V 85 265 V 400 V 380 415 V Nominal frequency 50 ...

Page 25: ... up terminal block screws 24 4 mm2 Max 0 6 Nm Communication and control terminal block screws 21 1 5 mm2 Max Multifunctional relay terminal block screws 22 1 5 mm2 Max 0 25 Nm IP65 cover fastening ring nut for installation on single REACT UNO 10Nm REACT BATT AP1 Ground connection point screws 35 2 0 Nm Plastic cover screws 11 2 0 Nm Screws for cover in connections area 09 1 2 Nm REACT MTR 1PH Comm...

Page 26: ...3 1 m m 740mm REACT POWE R ALAR M GFI ESC UP DOWN ENTE R REACT UNO REACT BATT 740mm REACT BATT 492mm 492mm 492mm 1478mm 2 3 1 m m REACT POWE R ALAR M GFI ESC UP DOWN ENTE R REACT UNO REACT BATT 740mm REACT BATT REACT BATT 492mm 492mm 492mm 1971mm 2 3 1 m m REACT POWE R ALAR M GFI ESC UP DOWN ENTE R REACT UNO REACT BATT 492mm Скачано с сайта интернет магазина https axiomplus com ua ...

Page 27: ...H The overall dimensions are given in mm Overall dimensions REACT MTR 3PH The overall dimensions are given in mm REACT MTR 1PH S U T A T S E R U S A E M INPUT 110 230 V 50 60 Hz 10 mA max 100 64 53 97 65 70 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 28: ... bracket are expressed in mm A B A A B B 94 850 280 163 280 25 25 25 25 0 A B 55 25 246 5 246 5 246 5 55 25 15 15 15 15 24 10 2 1 R EA C T POWE R ALAR M GFI ESC UP DOWN ENTE R R EA C T U N O R EA C T B AT T 2 8 Ø6 5 Ø6 5 1 2 13 7 11 8 7 50 43 99 4 99 4 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 29: ...racket are expressed in mm A A B B 2 8 Ø6 5 Ø6 5 1 2 13 7 11 8 7 50 43 99 4 99 4 2 1 2 1 RE AC T POWER ALARM GFI ESC UP DOWN ENTER RE AC T UN O RE AC T BA TT RE AC T BA TT B B A A 10 55 25 246 5 15 15 24 3 9 66 502 96 25 530 370 450 38 34 523 04 13 5 25 280 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 30: ...d to technical parameters that are continually being developed and improved and should therefore be considered approximate REACT UNO 3 6 TL REACT UNO 4 6 TL 90 91 92 93 94 95 96 97 98 99 100 Efficiency of Rated Output Power 520 Vdc 360 Vdc 160 Vdc 0 10 20 30 40 50 60 70 80 90 100 Efficiency curves 90 91 92 93 94 95 96 97 98 99 100 Efficiency of Rated Output Power 0 10 20 30 40 50 60 70 80 90 100 5...

Page 31: ...Power limiting may occur due to Adverse environmental conditions thermal derating Percentage of output power Over frequency of grid voltage Grid overvoltage U 10min Der Anti islanding Grid undervoltage High input voltage values High input current values The aforementioned power limits may vary depending on the grid standard of the country of installation Скачано с сайта интернет магазина https axi...

Page 32: ...se the inverter guarantees the maximum output power even at high temperatures provided the sun is not shining directly on it 0 10 50 15 59 20 68 25 77 30 86 35 95 40 104 45 113 50 122 55 131 60 140 Ambient temperature C and F 50 100 95 Nominal Output Power 90 85 80 75 70 65 60 55 45 40 35 30 25 20 15 10 5 Pout Vs Ambient temperature REACT UNO 4 6 TL 0 10 50 15 59 20 68 25 77 30 86 35 95 40 104 45 ...

Page 33: ... 85 80 70 65 60 55 1000 3280 1200 3937 1400 4593 1600 5249 1800 5905 2000 6561 Altitude mt and ft 2200 7217 2400 7874 2600 8530 2800 9186 3000 9842 Altitude Vs Max input voltage 50 75 100 Normalized temperature Tmax derated Tmax sea level 95 90 85 80 70 65 60 55 Derating Pout Vs Altitude 1000 3280 1200 3937 1400 4593 1600 5249 1800 5905 2000 6561 Altitude mt and ft 2200 7217 2400 7874 2600 8530 28...

Page 34: ...ting of the control algorithm For input voltages below 90Vdc the output power of the inverter could be different from zero should the battery be low Vin V Pout W 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 0 50 100 150 200 250 300 350 400 450 500 550 600 Pout 2 battery Pout 3 battery Pout 1 battery Pout No battery Pout Vs Vin The operating point of REACT inside the area of the diagram depen...

Page 35: ...s can only be charged from the grid while over 90Vdc the batteries can be charged from the photovoltaic system and or from the grid at the same time Vin V Pout W 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 0 50 100 150 200 250 300 350 400 450 500 550 600 5500 6000 Pcharge 3 battery Pcharge 2 battery Pin with battery Pin No battery Pcharge 1 battery Pin Vs Vin For input voltages below 90Vdc ...

Page 36: ...iring on the DC side of the inverter and subsequent distribution on the AC side A photovoltaic panel consists of many photovoltaic cells mounted on the same support A string consists of a certain number of panels connected in series An array consists of two or more strings connected in parallel Large photovoltaic systems can include multiple arrays connected to one or more inverters The greater th...

Page 37: ...REACT BATT battery pack It temporarily stores the unused energy from the photovoltaic generator The energy stored will subsequently be used whenever the demand for energy is greater than that produced by the generator REACT MTR energy meter It measures the energy at the connection point to the grid and communicates with REACT UNO in order to manage the storage system On the basis of domestic consu...

Page 38: ... max Load Manager Backup Reference Description A Photovoltaic generator B REACT system consisting of REACT UNO and REACT BATT C Meter for energy produced where required by national regulations D REACT MTR E Exchange meter on the supply point of the grid F Electricity grid G Domestic utilities connected to the back up output H Domestic utilities I Wi FI Router L Aurora Vision web portal M Smartphon...

Page 39: ...imum limit on active power fed into the grid that was set by the operator may be exceeded in this case the REACT system can automatically limit the feeding of active power to the grid 3 When the energy supplied by the PV generator is insufficient to power the utilities the system supplies the energy stored in the batteries thus enabling greater energy self sufficiency 4 When the battery is complet...

Page 40: ... interface or set by the display or through the configuration software Aurora Manager LITE Power feeding management modes vary according to the country of installation and the grid companies For detailed information on the parameters and characteristics of this function please contact ABB directly Limiting the active power fed into the grid The inverter if enabled and set using the display or the ...

Page 41: ...ers Optimisation of self consumption REACT is equipped with an storage system 2kWh base system expandable up to 6kWh which enables use of the photovoltaic energy at different times The energy stored in the battery during the day can be used in evening hours or whenever photovoltaic production is not sufficient to meet consumption by domestic utilities Compared to a photovoltaic system without stor...

Page 42: ...f grid Back up Mode Manual 4 Conditions necessary to activate the back up function are Agreement of manual user by pressing Enter key on display for at least 5sec External command signal Communication and control signal terminal block 21 terminal 1 3 Lack of grid Back up Mode Auto 1 A necessary condition for activating the back up function is External command signal Communication and control signa...

Page 43: ... T R T R RTN Remote control R R Alarm N C N O C L N AC Output AC Backup Output REACT UNO Charger Discharger DC DC Protection STOP REACT BATT AP1 Opt REACT BATT AP1 Opt Switch T R T R RTN T R 1 T R RTN WIFI Load Manager Box RS485 RTU Modbus RS485 Meter Protection BMS Battery pack Protection BMS Battery pack DC DC DSP contr DC AC DSP contr µP Control circuit 2 3 4 5 6 7 8 A B C D Скачано с сайта инт...

Page 44: ...he equipment both when connected to the grid and when in back up mode REACT BATT AP1 state of health SOH The state of health SOH is defined as the relation between the current capacity and the nominal capacity of the battery 2kWh The SOH trend is constantly decreasing for natural aging linked to the use of the battery and is not an indication of its malfunction The downward inclination of the degr...

Page 45: ...withcorrectinformation Theymustthereforereadandcomply with the technical information provided in the manual and in the attached documentation The instructions provided in the manual do not replace the safety devices and technical data for installation and operation labels on the product and they do not replace the safety regulations in force in the country of installation The manufacturer is willi...

Page 46: ...perate in environments that are particularly inflammable or explosive IThe customer and or installer must appropriately train operators or anyone who may come into close proximity of the equipment and highlight with notices or other means where necessary the hazardous areas or operations at risk magnetic fields hazardous voltages high temperatures possible discharges generic hazard etc Keep out of...

Page 47: ...arges or in general clothing that can compromise personal safety All operations on the equipment should be performed with suitably insulated clothing and tools E g insulating gloves class 0 RC category Maintenance operations may only be performed after the correct procedure for taking the equipment out of service has been carried out Personnel must NOT go near the equipment with bare feet or wet h...

Page 48: ...EACT BATT AP1 must be used solely with the inverter REACT UNO XX DO NOT touch the battery pack directly if there is a leak of electrolyte material Should the electrolyte material come into contact with the eyes wash the eyes with plenty of fresh water as soon as possible without rubbing them Then consult a doctor If no treatment is applied there could be problems for the eyes DO NOT touch the batt...

Page 49: ... might have a shorter lifespan If the battery pack has signs of rust a bad smell or any anomaly on first being used do not use the equipment If the skin or clothes come into contact with electrolyte material which has leaked from the battery pack wash them in plenty of fresh water as soon as possible otherwise it might cause inflammation of the skin Final installation of the equipment must not hin...

Page 50: ...of surfaces at temperature transformers accumulators coils etc can cause burns Also be careful not to block the cooling slits or systems of the equipment Use suitable protective equipment or wait for the parts to cool down before switching on the equipment Inadequate cleaning compromises cooling and does not allow the safe ty labels to be read Clean the equipment labels and work environment adequa...

Page 51: ...an be done using pallet trucks or forklifts by picking up the pallet in the area intended for lifting The transport of individual boxes containing the equipment must be done using suitable means and with careful supervision by authorised staff The accident and safety prescriptions for handling and lifting operations must be complied with 4 Lifting and transport Скачано с сайта интернет магазина ht...

Page 52: ...EACT BATT there is a high risk of fire Keep the REACT BATT in a dry place Relative humidity not condensing 5 95 Handle and treat packages carefully Avoid unnecessary movements of the REACT BATT Ambient temperature allowed during storage 20 C 40 C Maximum height above sea level a s l 2 000 m For the rules on storing the battery refer to the regulations in force in the country concerned Handling of ...

Page 53: ...must be suitable for bearing the weight of the equipment Do not lift several units or parts of the equipment at the same time unless otherwise indicated Equipment weight Risk of injury due to the weight of the equipment Take care during lifting and transport Table Weights Device Weight kg lb Lifting points REACT UNO 3 6 4 6 TL 30kg 66 1lb 4 2 people REACT BATT AP1 37kg 81 5lb 4 2 people REACT POWE...

Page 54: ...ee full operation and the validity of any guarantees the REACT BATT must be put into service within 3 months at most of the date of delivery by ABB to the recipient of the goods Should the guarantee be used the date of commissioning must be demonstrated by submitting to ABB the commissioning report or the invoice to the end user The ambient temperature allowed for transport is from 20 C to 40 C Th...

Page 55: ...The general standards on packaging must be complied with The limitations for particular substances must be complied with Sections 4 1 1 6 4 1 1 7 and 4 1 6 8 ADR must be complied with The 1000 units rule can be applied only if the following conditions are met Respect of a maximum quantity of 1000 units 333 kg Presence of a 2 kg extinguisher for each vehicle Marking and labelling of the packaging W...

Page 56: ...and make sure all the components are present If any defect or damage is detected please stop contact the carrier and also promptly inform the ABB Service List of components supplied Inside the package the following components required to correctly install the inverter are supplied Components supplied together with the inverter REACT UNO Components available for REACT UNO Quantity Connector for con...

Page 57: ... the interface and manageme nt software for the product are available at the website XXXX XXXX XXXX XXXX XXX XXXX XXXX XXXX XXXX XXX ABB solar inverters Technical documentation 1 Components supplied together with the inverter REACT BATT Components available for REACT BATT Quantity Cable conduit male 1 In addition to what is explained in this guide the safety and installation information provided i...

Page 58: ...ture and operation of the unit may install the inverter The installation must be performed by qualified installers and or licensed electricians in ac cordance with the existing regulations in the country of installation The removal of the inverter panels covers allows access to the area dedicated to service personnel the operator is not authorized to access this area Connection of the photovoltaic...

Page 59: ...he inverter with a resulting decreased energy production by the system premature wear of the electrical electromechanical components premature wear of the mechanical components gaskets and of the user interface display reduction in performance lifetime and possible damage of the battery pack Always ensure that the flow of air around the inverter is not blocked so as to prevent overheating Do not i...

Page 60: ...stem with possible reduction in the lifetime of the batteries T3 Partial operation of the battery which limits its functioning to discharge only T4 Operation limited to the inverter part only Management of the battery is disabled 20 10 0 5 35 40 45 55 T1 T2 T3 T4 C T2 T3 T4 Consult the technical data to check the required environmental conditions protection rating temperature humidity altitude etc...

Page 61: ... cannot be met the inverter could undergo derating due to high temperature because of poor heat dissipation The installation must take account of any electrical devices e g lamps switches etc which must be at least 60cm from the equipment These distances must be maintained also to facilitate the circulation of the air needed to cool the unit and to facilitate the operations to install maintain har...

Page 62: ...ugs in the holes and fix the bracket to the wall using 4 screws with washers A supplied REACT POWER ALARM GFI ESC UP DOWN ENTER REACT UNO Lift and fasten the REACT UNO 03 to the wall bracket 01 by inserting the springs that are on the bracket itself into the 2 holes on the rear bracket of the REACT UNO 03 Risk of injury due to the weight of the equipment 01 A A A A 4 x Ø 10 mm Wall installation of...

Page 63: ...njury due to the weight of the equipment REACT POWER ALARM GFI ESC UP DOWN ENTER REACT U NO REACT BATT REACT BATT REACT POWE R ALAR M GFI ESC UP DOWN ENTER REACT UNO B B B B Anchor the lower part of the REACT to the wall by installing 4 plugs 10 mm diameter supplied Then screw in 4 screws with washers into the holes on the lower side of the equipment Скачано с сайта интернет магазина https axiompl...

Page 64: ...move the metal covers of the compartments for the electric connections 16 screws in total Remove the protective cover from the support of the Wi Fi antenna 52 located on the lower part of the REACT UNO 03 and install the Wi Fi antenna 53 by screwing it into the specific connector Скачано с сайта интернет магазина https axiomplus com ua ...

Page 65: ...l protective clothing and or equipment such as insulating gloves Proceed with installation of the REACT MTR Insertthebatterypackconnection cables which come out of the inverter into the REACT BATT 14 using the hole present on the side of the mechanical cover Feed the cables into the cable conduit male supplied with the REACT BATT 14 Insert the cable conduit male 36 into the REACT BATT 14 and screw...

Page 66: ...70 mm Install four 10mm diameter wall plugs in the holes and fix the bracket to the wall using 4 screws with washers A supplied REACT POWER ALARM GFI ESC UP DOWN ENTER REACT UNO Lift and fasten the REACT UNO 03 to the wall bracket 01 by inserting the springs that are on the bracket itself into the 2 holes on the rear bracket of the REACT UNO 03 Risk of injury due to the weight of the equipment 01 ...

Page 67: ...ing 2 plugs 10 mm diameter supplied Then screw in 2 screws with washers into the holes on the lower side of the equipment Remove the plastic cover installed on the REACT UNO 03 8screwsintotal Thenremovethe metal cover from the compartment for the electric connections 8 screws in total Скачано с сайта интернет магазина https axiomplus com ua ...

Page 68: ... the specific connector Disconnect the cables connecting to the battery unit in particular a the communication service cable b the power cable c the ground connection cable Then remove the cable conduit cabling Remove the fastening ring nut of the cable conduit The wing nut must be kept since it will be used again to set the sealing cover IP65 Скачано с сайта интернет магазина https axiomplus com ...

Page 69: ... the battery unit Position the cover outside the REACT UNO and screw the fastening ring nut on the internal side Make the electric connections using personal protective clothing and or equipment such as insulating gloves Proceed with installation of the REACT MTR Скачано с сайта интернет магазина https axiomplus com ua ...

Page 70: ...of the REACT MTR 1PH mono phase The indications set out below are necessary to connect the REACT MTR to the REACT sy stem Always refer to the specific documentation supplied with the REACT MTR 1PH The energy meter REACT MTR 1PH 54 is a DIN rail device 3 modules and must be installed where the electricity supply is mono phase To avoid risks of electrical shock all wiring operations must be carried ...

Page 71: ...ow indicates the supply point of the electric energy as indicated in the diagram Once the connection stage is finished the correct installation of the REACT MTR 1PH must be verified 54 Power the REACT MTR 1PH while keeping the REACT system off Action a load of at least 50W in the house so that the REACT MTR records drawing of current from the grid Check that the LED MEASURE red is permanently on T...

Page 72: ...ction terminal block 59 and tighten the screws tightening torque 2 0 Nm Take note of the phase to which the REACT system is connected this information will be requested when the system is commissioned Connect the cables of the serial line A 37 B 36 and C 37 on the terminal block 60 set on the rear of the REACT MTR 3PH 58 and tighten the screws tightening torque 0 25 Nm Subsequently the cable must ...

Page 73: ...s to access Press to enable the change in the value Press repeatedly until the display shows Modbus Press to confirm the change Press for two seconds to return to the RS485 menu 5 Press repeatedly until the display shows Baud rate Press to access Press to enable the change in the value Press repeatedly and select 57600 Press to confirm the change Press for two seconds to return to the RS485 menu 6...

Page 74: ...ification of leakage to ground Do not connect the strings if a leakage to ground has been detected as the inverter might not connect to the grid Selection of differential protection downstream of the inverter AllABB string inverters marketed in Europe are equipped with a device for protection against ground faults in accordance with the safety standard IEC 62109 2 sections 4 8 2 and 4 8 3 of the S...

Page 75: ...r protection of theAC line on the basis of the information above with regard to the differential protection integrated in ABB inverters it is not necessary to install a type B differential switch In accordance with article 712 413 1 1 1 2 of Section 712 of IEC Standard 64 8 7 we hereby declare that because of their construction ABB inverters do not inject ground fault direct currents The use of an...

Page 76: ...ized in order to pre vent unwanted disconnections of the inverter from the grid due to high impedance of the line that connects the inverter to the power supply If the impedance is too high it causes an increase in the AC voltage which on reaching the limit set by the standards in the country of installation causes the inverter to switch off The table shows the maximum length of the line conductor...

Page 77: ...AC output terminal block 25 by passing the cables through theAC cable gland 48 Strip 10mm of sheathing from the cables to connect to the AC grid then insert into the inverter theAC line cable making it pass through theAC cable gland 48 the maximum diameter of the cable accepted by the cable gland is from 10 to 17 mm Connect on the cable gland 25 the ground cable yellow green to protect against con...

Page 78: ... 49 side inside the REACT UNO The installation is carried out a position the filter on the internal side of the cable gland b Screw the filter on the thread of the cable gland a b Insert the grid cable into the inverter using theAC cable gland 49 calledAC 1 M25 equipped with toroid and make the connections to theAC output terminal block 24 Use a properly sized tripolar cable and check the tightnes...

Page 79: ... 2 5 11 m 4 19 m The values are calculated in nominal power conditions considering loss of power along the line no greater than 1 use of copper cable with HEPR rubber insulation and positioned in open air Load protection switch AC disconnect switch for back up output To protect the AC back up connection line of the inverter a device must be installed to protect against maximum current and leakage ...

Page 80: ...accepted by the cable gland is from 10 to 17 mm Connect on the cable gland 24 the ground cable yellow green to protect against contact marked by the symbol the neutral cable usually blue to the terminal marked by the letter N and the phase cable to the terminal marked by the screen print L every individual terminal of the terminal block accepts a cable with maximum section of 4 mm It is necessary ...

Page 81: ...y to leverage the full power of the inverter output on a single channel MPPT MPPT1 MPPT2 The dual MPPTstructure however allows management of two photovoltaic generatorswhichareindependentofeachother oneforeachinputchannel and which may differ between themselves with regard to installation conditions type and number of photovoltaic modules connected in series A necessary condition for the two MPPT ...

Page 82: ... orientation to SOUTH Thephotovoltaicgeneratorconnected to each of the inputs has a lower power than the power limit of the single input channel AND a maximum current lower than the current limit of the single input channel The condition is advisable from a system energy production viewpoint not from the point of view of the operation of the inverter The photovoltaic generator is made up of string...

Page 83: ... which must be selected during the guided setup for commissioning the system is INDEPENDENT Configuration of parallel connected channels This configuration uses the two input channels MPPT connected in parallel This means that the jumper supplied between the positive poles of the DC MPPT1 connectors 28 and the DC MPPT2 connectors 27 must be installed and that the mode which must be selected during...

Page 84: ... of each string located on the lower side of the REACT UNO mechanism are used 46 47 Connect all the strings required by the system always checking the seal of the connectors Thenumberofconnectionsforeachinputchannelis2pairsofconnectors Connect directly the individual input strings to the REACT UNO Should it be necessary to make parallel strings outside the inverter the maximum current allowed by t...

Page 85: ...ou must ensure that covers are installed to the connectors and install any which are missing ThisisnecessarybothfortheinvertergradeIPseal andtoavoiddamagetothefreeconnector which may be used at a later time IP54 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 86: ...ng part on the manufacturer s website or with ABB Using corresponding parts that are not compliant with the quick fit connector models on the inverter could cause serious damage to the unit and lead to invalidation of the warranty CAUTION To avoid damage to the equipment when attaching cables pay particular atten tion to polarity 1 WEIDMÜLLER PV Stick quick fit connectors Installation of Weidmülle...

Page 87: ...tor limits Apply the terminal to the conductor using the designated pliers Weidmüller CTF PV WM4 1222870000 Insert the cable with the terminal into the interior of the connector until you hear the click indicating that the terminal is locked inside the con nector Click Firmly tighten the cable gland using the relevant tool to finish the ope ration 2 0 2 5 Nm WEIDMÜLLER SET MULTI TOOL PV 1217280000...

Page 88: ...ith the connector limits Apply the terminal to the conductor using the designated pliers Multi Contact 32 6020 19100 Insert the cable with the terminal into the interior of the connector until you hear the click indicating that the terminal is locked inside the con nector Click Firmly tighten the cable gland using the relevant tool to finish the ope ration 2 5 Nm Multi Contact 32 6024 12mm 4 6mm 5...

Page 89: ...th the connector limits Apply the terminal to the conductor using the designated pliers Amphenol H4TC0002 Insert the cable with the terminal into the interior of the connector until you hear the click indicating that the terminal is locked inside the con nector Click Firmly tighten the cable gland using the relevant tool to finish the ope ration 2 6 2 9 Nm Amphenol H4TW0001 7mm 4 6mm 7 6 9 3mm 2 С...

Page 90: ... of the four service cable glands 51 available named OUT 1 OUT 2 OUT 3 and OUT 4 51 They are M20 service cable glands 51 and can take a cable with a diameter of 7 mm to 13 mm Two hole gaskets are supplied to be inserted into the cable gland which allow two separate cables with cross section of up to 5 mm to pass through A B C Скачано с сайта интернет магазина https axiomplus com ua ...

Page 91: ...ModBus communication line RS485 PC 13 T R of the RS485 PC communication line 15 T R of the RS485 PC communication line 17 Reference RTN of the RS485 PC communication line RS485 METER 14 T R of the RS485 METER communication line 16 T R of the RS485 METER communication line 18 Reference RTN of the RS485 METER communication line 19 20 Ground terminal Description of multifunctional relay terminal bloc...

Page 92: ...enabled in the relevant menu If the remote control function is disabled the switching on of the inverter is dictated by the presence of the normal parameters that allow the inverter to connect to the grid Iftheremotecontrolfunctionison besidesbeingdictatedbythepresence of the normal parameters that allow the inverter to connect to the grid switching on the inverter also depends on the state of ter...

Page 93: ...o make a daisy chain connection in out of multiple inverters Connection of a monitoring system to the RS485 M B communication line consists of first connecting all the units in the chain in the daisy chain in out configuration respecting corresponding signals and then activating the communication line termination resistance in the last element in the chain by setting the switch for RS485 M B line ...

Page 94: ...st in the system Each inverter is supplied with one 1 preset RS485 address and with an RS485 M B line termination switch 20 in the OFF position Connect the signals respecting the following positions Terminal name Terminal number Description RS485 M B 7 8 T R of the RS485 M B communication line 9 10 T R of the RS485 M B communication line 11 12 Reference RTN of the RS485 M B communication line For ...

Page 95: ...T UN O REAC T BAT T REAC T POWER ALARM GFI ESC UP DOWN ENTER REAC T UN O REAC T BAT T RS485 USB Software Aurora Manager RS 485 HALF DUPLEX RESET TX RX PWR OK RTN RX D TX D N C USB B Type RS232 RS485 PVI USB RS232_485 RS232 485 Sel RS232 RS485 RESET TX RX PWR OK USB B Type RS232 RS485 RS232 485 SEL RS232 RS485 RTN RX D TX D N C PVI USB RS232_485 18 When connecting a single inverter to the monitorin...

Page 96: ...tic impedance of Z0 120 Ohm like the one shown in the following table Signal Symbol T R T R SH RTN T R T R SH RTN Positive data T R Negative data T R Reference RTN Shield SH Shield continuity must be provided along the communication line and must be grounded at a single point using terminal 19 or 20 Connection of conductors with RJ45 connectors 17 ThetwoRJ45connectors A and B availableforRS485PCco...

Page 97: ...specting corresponding signals and activating the termination resistance of the communication line via the RS485 METER line termination switch 19 to the ON position RS485 METER REACT POWER ALARM GFI ESC UP DOWN ENTER REA CT UNO REA CT BATT REACT MTR 1PH S U T A T S T S E T E R U S A E M INPUT 110 230 V 50 60 Hz 10 mA max 19 Do not connect units in a chain following the daisy chain in out configura...

Page 98: ...line For long distance connections it is preferable to use a shielded twisted pair cable with characteristic impedance of Z0 120 Ohm like the one shown in the following table Signal Symbol T R T R SH RTN T R T R SH RTN Positive data T R Negative data T R Reference RTN Shield SH Shield continuity must be provided along the communication line and must be grounded at a single point using terminal 19 ...

Page 99: ...he relay provided they comply with the following requirements Alternating current Maximum Voltage 240 Vac Maximum Current 1 A Direct current Maximum Voltage 30 Vdc Maximum Current 0 8 A Cable requirements External diameter from 5 to 17 mm Conductor cross section from 0 14 to 1 5 mm2 This contact can be used in different operating configurations that can be selected by accessing the Inverter Settin...

Page 100: ... The relays are not power components and must be used for example to control a power relay installed outside the REACT system If the external device is connected directly to the relays the following characteristics must be respected Technical data for each relay Maximum Power 250W Maximum voltage 250Vac Maximum current 1A Protection Fuse non resettable For further details relating to the external ...

Page 101: ...u do not have suitable qualifications to work on this equipment or similar products you are unable to understand how it works you are not sure what will happen when the buttons or switches are operated you notice any operating anomalies there are doubts or contradictions between your experience the manual and or other operators ABB cannot be held responsible for damage to the equipment or the oper...

Page 102: ...b02 b08 b23 b01 b03 b09 b11 b10 b20 b12 b13 b14 b15 b16 b17 b18 b19 b21 b24 b22 b25 b26 b04 b06 b07 b05 Ref Description b01 Indicates the transmission and reception of data through the RS485 line b02 Indicates the presence of the RS485 communication line b03 Indicates the presence and enablement of the WiFi communication line b04 Reports an active power derating for out of range input voltage or p...

Page 103: ...present Grid voltage present and within parameters set by the standard grid b20 Cyclic display of the input parameters b21 Cyclic display of storage parameters batteries b22 Indicates the status of the battery charge b23 When the ENTER key is pressed cyclic display of the parameters can be blocked or cyclic b24 Cyclic display of the output parameters b25 Cyclic display of the parameters relating t...

Page 104: ...plied from the storage system to the house the line between the symbol representing the inverter and the battery has the arrow pointed towards the inverter This means that the battery is being charged 1 7kW is drawn from the grid the line between the symbol representing the meter and the grid has the arrow pointed towards the meter This means that the power is drawn from the grid Example 4 Photovo...

Page 105: ...ch dot represents 300Wh full scale 3KWh of average energy The time scale is 24 hours in 1 hour intervals Diagram BATTERY SOC This diagram shows the state of charge of the battery Each dot represents 5 full scale 100 The time scale is 24 hours in 1 hour intervals Diagram PW TO LOAD This diagram shows the energy used to fulfil the request from domestic loads Each dot represents a value of 250Wh full...

Page 106: ...he inverter has detected an anomaly The type of problem will be shown in the display Indicates that the inverter is functioning correctly When the unit is commissioned while the grid is checked this LED blinks If a valid grid voltage is detected the LED remains continuously lit as long as there is sufficient sunlight to activate the unit Otherwise the LED will continue to blink until the sunlight ...

Page 107: ... variation of some data is reserved exclusively for specialized and qualified staff The incoming voltage must not exceed the maximum values shown in the technical data section 2 in order to avoid damaging the equipment Consult the technical data for further details During operation check that the environmental and logistical conditions are correct see installation chapter 5 Make sure that envirome...

Page 108: ...485 port Con tact the ABB support service with any queries about device compatibility Measurement tolerance The data supplied by the inverter may differ from measurements taken by certified measuring instruments e g output meters multimeters and grid analysers since the inverter is not a measuring instrument it has wider tolerances for the measurements it makes The tolerances are generally 5 for r...

Page 109: ...erter with input voltage from the photovoltaic generator Where the system is powered by the photovoltaic generator DC make sure irradiation is stable and adequate for the REACT s commissioning procedure to be completed Close the external AC disconnect switch downstream of the inverter thus applying grid voltage to the inverter Oncepowered theREACTwillautomaticallycreateaWi Finetworkthat will be vi...

Page 110: ...T system The setup is broken down into 7 steps Assisted setup STEP 1 Settings of menu language Time zone Grid standard Each of the above mentioned settings has a drop down menu from which preset parameters can be selected Press Avanti Next at the end of the settings to move on to setup step 2 Setting the language refers to the webserver language not the language of the display me nus on the REACT ...

Page 111: ...password for the destination network if necessary and start the connection attempt it will take a few seconds If it is not possible to connect the REACT to the Wi Fi network or you do not want to do so select the Procedi in modalità AP Continue in AP mode button In this situation communi cation between the REACT and the tablet smartphone PC will continue to be point to point Once the REACT is asso...

Page 112: ...router replacement of router different SSID without the necessary setting updates Assisted setup STEP 3 Setting date and time Fill in the fields relating to date time and time zone If the inverter is connected to the internet the settings will be filled in automatically and it will not be possible to edit the fields Date and time The date and time shown are provided by the inverter or have been en...

Page 113: ...e internet the Longitude and Latitude fields are filled in automatically Check that they are correct Administrator password Pay particular attention and make a note of the administrator password that will enable you to do advanced system setup User password Pay particular attention and make a note of the user password that will enable you to do basic system setup The No Password box can be selecte...

Page 114: ... Type of battery unit REACT BATT installed 1 No battery when the REACT system is used without a battery Select the number of battery units installed 2 REACT BATT AP1 Once the type of meter REACT MTR and number of battery units RE ACT BATT are selected the system will check the settings entered gi ving confirmation or an error message if the setup was incorrect The guided system setup can be contin...

Page 115: ...order to avoid feeding the grid with power greater than PDC x Plim where PDC is the power of the photovoltaic ge nerator W and Plim is the output power limit with respect to PDC The two variables can be set during the REACT commissioning sta ge KfW The REACT system automatically manages power flows in order to fulfil the requirements of the KfW incentive programme available in Germany Photovoltaic...

Page 116: ...e app To register the system on Aurora Vision click on the link shown in the figure the REACT must be connected to the internet Registration with Aurora Vision The setup procedure is completed Access the main page of the REACT web server by clicking on FINITO Finished To receive system updates remotely To maximise your photovoltaic system s performance To receive notifications in the event of alar...

Page 117: ...b update file on the SD Card The file must not be com pressed and or nested inside folders Switch the inverter off by physically disconnecting the AC and DC side as well as any voltages connected to the multi function relay then open the inverter front cover Insert the SD Card into the memory card holder Start the inverter The inverter display prompts for confirmation to launch the update The upda...

Page 118: ...yellow red Disconnection from the grid Indicates no grid voltage This condition does not allow the inverter to connect to the grid the inverter display shows the message Missing Grid green yellow red Indication of Warning W message codes or Error E warning codes Indicates that the inverter control system has detected a warning W or error E The display shows a message indicating the type of problem...

Page 119: ...the constant or intermittentlightingofthespecificLED thedisplay 07 alsoshowsamessage identifying the operation which is being carried out or the defect anomaly recorded see specific chapter In the event of malfunctioning it is extremely dangerous to try to eliminate the fault personally The instructions below must be followed scrupulously if you do not have the necessary experience and training to...

Page 120: ...duced day Today s savings earnings Value and graphical representation of the energy fed into or taken from the grid Power fed into grid bars and arrow towards symbol Power taken from grid bars and arrow towards the symbol Zero exchange with the grid central down arrow with words ZERO NET POWER E tot Energy produced since the inverter was commissioned E par Partial energy produced since the last re...

Page 121: ...DOWN UP Alarm description Warning Error xxx Inverter OK Mon 22 Jan 15 55 DOWN UP DOWN UP Inverter status The code for any malfunction will be displayed Date and time as set on the inverter Presence of Errors Warnings No Errors Warnings Pout Instantaneous output power backup Backup operating modes of backup output Vin 1 Input voltage channel 1 Vin Input voltage Iin 1 Input current channel 1 Iin Inp...

Page 122: ...W Rel Measures Voltage Active Power Line current Load current Frequency Meter model Meter Address Meter com Battery General Load Manager info Relay Status WIFI Logger Settings Info Part No Serial No View IP View Mode Restore AP System Password 0000 Password 0000 Password 0000 Settings Info Nom Cap Measures Ibat Vbat Pbat RE SOC SOH RT Battery Model Battery Packs Password 0000 Pack 1 Settings Info ...

Page 123: ...he grid today E 7d energy fed into the grid in the last 7 days E 30d energy fed into the grid in the last 30 days E 365d energy fed into the grid in the last 365 days E tot total energy fed into the grid 5 Ener to load This section of the menu displays the statistics relating to the energy used to fulfil the requests from residential loads In particular E day energy used for residential loads toda...

Page 124: ...s up the numerical scale from 0 to 9 ENTER confirms and moves to next digit ESC returns to the previous digit from right to left Press ESC several times to return to the previous menus 1 Set Time Allows you to set the current date and time not counting summer time 2 Set Cash This section of the menu allows you to set the name of the currency and the value given to 1 kWh of energy produced Setting ...

Page 125: ...assword If the Password is lost you will not have access to the inverter since there is no Reset function for security reasons System Info The Info menu is only available if previous firmware updates have been carried out via SD Card Select Info to access the following sub menus 1 SD Update Info This section of the menu visible only when SD card is inserted is used to display the outcome of the fi...

Page 126: ...icien Ener from grid Ener to grid Ener to load PV en to load PV ener Settings Info Measures Set time Password 0000 Set cash Set RS485 com Country Select New password SD Update Info Energy Policy Inverter Statistics Settings Vstart Input mode Input UV Delay Service Info Part No Serial No Firmware Remote ON OFF MPPT Scan Power Limit Reactive Power Autotest Alarms Backup Lifetime Partial Today Last 7...

Page 127: ...ay s production calculated using the currency and conversion coefficient set in the relevant section of the Settings menu CO2 Amount of CO2 saved daily 4 Last 7 days This section of the menu displays the statistics for the last 7 days E 7d Energy produced over the last 7 days Er 7d Val Value of production over the last 7 days calculated using the currency and conversion coefficient set in the rele...

Page 128: ...ion of the menu displays the statistics for the last 365 days E 365d Energy produced over the last 365 days Er 365d Val Value of production over the last 365 days calculated using the currency and conversion coefficient set in the relevant section of the Set tings menu CO2 Amount of CO2 saved over the last 365 days 7 User Period This section of the menu displays the statistics for a period chosen ...

Page 129: ...the site make sure you have all the information required to calculate your password Inverter Model Serial Number and week of manufacture of the Inverter When you have a password you can set the parameters in the menu Changing the above mentioned parameters may prevent disconnection from the grid if the new values exceed those given in the standards of the country of installation If these parameter...

Page 130: ...hold extended range En Dis F Enable Disable the parameter Value F Set tripping value Time F Set tripping time Set Connect Set U Connect Max permissible voltage during checks prior to grid connection Set U Connect Min permissible voltage during checks prior to grid connection Set F Connect Max permissible frequency during checks prior to grid connection Set F Connect Min permissible frequency durin...

Page 131: ...ion This function is useful when there are areas of shade on the PV generator which may create several points of maximum power on the operating curve E D MPPT Scan Enables Disables the scan for identifying the maxi mum power point of the system Scan Interval This section allows you to set the time between scans Remember that the shorter the scan interval the greater the loss of pro duction due to ...

Page 132: ...heAurora Manager Lite setup software Q f U reactive power as a function of the grid voltage measured by the inverter To enable this mode select Enable and then OK using the UP DOWN arrows When it has been enabled Load std curve will appear on the display allowing you to set the following regulation curve Q Pn Vout 0 0 2 0 3 0 36 0 1 0 1 0 36 0 3 0 2 210 220 230 240 250 The curve can be modified us...

Page 133: ...isconnection the relay is in its resting position INVERTER RUN PRODUCTION GRID DISCONNECTION NO PRODUCTION GRID RECONNECTION t basedonCountryStandard DISCONNECTION CAUSEISSTILL PRESENT Yes No N C N O N C N O N C N O Relay State Idle Relay State Idle Relay State Switched tics onsumpti ufficien from grid to grid to load to load r gs es me d 0000 sh S485 com y Select ssword ate Info Policy Inverter S...

Page 134: ... W003 W004 W005 W006 W007 In the presence of W003 W004 W005 W006 W007 signalling the alarm contact switches to then reset itself at the end of the alarm signal This means that during the absence of grid voltage display message Missing Grid the alarm contact remains in its resting position cs nsumpti fficien om grid grid load to load e 0000 h 85 com Select sword te Info Policy Inverter Statistics S...

Page 135: ... alarm contact cyclically switches from its resting state to its activated state In the presence of W002 signalling Input UV input voltage below the limit of operation the alarm contact switches to then reset itself at the end of the alarm signal This means that during the reduced input voltage display message Waiting Sun the alarm contact remains in its resting position In the presence of W003 W0...

Page 136: ...en the inverter re turns to its normal operating state and reconnects to the grid Alarms for which the relay is activated E001 E002 E003 E004 E005 E006 E007 E009 E010 E011 E012 E013 E014 E015 E016 E017 E018 E019 E020 E021 E022 E023 E024 E025 E026 E027 E028 E029 E030 E031 E032 E033 E034 E035 E036 E037 E046 E050 E053 E054 E055 E056 E057 E058 E077 E078 E081 E084 E089 W003 W004 W005 W006 W007 cs nsump...

Page 137: ...he alarm condition is persistent the relay will remain activated status switched Ext configurable alarm display text Al Conf Ext In this mode it is possible to configure the behaviour of the alarm relay according to an external error table which can be setup with the Aurora Manager LITE software In the table it is possible to select the alarms tics onsumpti ufficien from grid to grid to load to lo...

Page 138: ... manufacture of the equipment 3 Firmware Lets you see the revision of the firmware and the Update version if the inverter has been updated with a tib type firmware package installed on the equipment cs nsumpti fficien om grid grid load to load e 0000 h 85 com Select sword te Info Policy Inverter Statistics Settings Vstart Input mode Input UV Delay Service Info Part No Serial No Firmware Remote ON ...

Page 139: ... graph that will be displayed in the graph section of the display In particular Auto Displays the 5 graphs listed below cyclically changing the graph every 5 seconds PW Vs Grid Display of energy fed into and taken from the grid PW Vs Batt Display of energy fed into and taken from the battery Battery SOC Display of state of charge of the battery PW to Load Display of the energy used to fulfil the r...

Page 140: ...s you to set the Baud Rate 19200 57600 115200 Parity It allows you to set the Parity bit None Even Odd Meter Info Select Info to access the following sub menus 1 Type Displays the type of meter connected to the REACT system 2 Part No Displays the model code 3 Serial No Displays the serial number and week and year of manufacture of the equipment 4 FW Rel Lets you view the revision of the firmware i...

Page 141: ...alue Depending on the type of meter connected it is pos sible to have a single value L1 for the single phase or three values L1 L2 and L3 for the three phase 2 Active power Value of active power delivered by system Depending on the type of meter connected it is possible to have a single value L1 for the single phase or three values L1 L2 and L3 for the three phase 3 Line current Value of current f...

Page 142: ...access the following sub menus 1 Nom Cap Displays the nominal capacity in Ah of the batteries connected to the REACT system Battery General Measure Select the Measure menu to access the following sub menus 1 Ibat Battery current value 2 Vbat Battery voltage value 3 Pbat Battery power value 4 RE Value of energy available in storage system Meter Settings Info Type Part No Serial No FW Rel Measures V...

Page 143: ...he numerical scale from 0 to 9 ENTER confirms and moves to next digit ESC returns to the previous digit from right to left Press ESC several times to return to the previous menus 1 Pack 1 Enable Enables or disables the operation of the REACT BATT 1 2 Smoke Sensor Enables or disables the control of the brightness sensor installed inside the REACT BATT relating to battery pack 1 Battery Pack 1 Info ...

Page 144: ... value 2 Vbat Battery pack 1 voltage value 3 Pbat Battery pack 1 instantaneous power value 4 Tbat Battery pack 1 temperature value 5 FCC Full charge capacity Current capacity of battery pack This value is con tinuously updated based on the operation of the storage system Meter Settings Info Type Part No Serial No FW Rel Measures Voltage Active Power Line current Load current Frequency Meter model ...

Page 145: ...oned 13 RT Remaining time Time remaining before the battery runs out calculated based on actual absorption 14 CC Cycle Counter Counter of number of cycles completed by the battery pack Meter Settings Info Type Part No Serial No FW Rel Measures Voltage Active Power Line current Load current Frequency Meter model Meter Address Meter com Battery General Load Manager info Relay Status WIFI Logger Sett...

Page 146: ... password is 0000 Enter the password using the keys on the display DOWN scrolls down the numerical scale from 9 to 0 UP scrolls up the numerical scale from 0 to 9 ENTER confirms and moves to next digit ESC returns to the previous digit from right to left Press ESC several times to return to the previous menus 1 Restore AP This section of the menu allows you to restore the Access Point mode of the ...

Page 147: ...oreattemptinganyworkontheinverter waitenoughtimeforthestoredenergytobedischarged Remove the front covers Under these conditions both wiring boxes have hazardous voltages highlightedbythesymbol whiletheotherareasmaybefreelyaccessed J6 J5 BATT COMM BUS BATT COMM BUS 3 J 4 J M O C O I Y R E T T A B I T L U M K N I L M O C O I MULTI BATTERY DC POWER D1 D2 D3 OFF J2 J1 J7 PE 120 Ω ON BATTERY ADDRESS SE...

Page 148: ...For cleaning DO NOT use rags made of filamentary material or corrosive products that may corrode the equipment or generate electrostatic charges Avoid temporary repairs All repairs should be carried out using only genuine spare parts The maintenance technician is to promptly report any anomalies DO NOT allow the equipment to be used if problems of any kind are found Always use personal protective ...

Page 149: ...ere is no monitoring system check the alarms and errors log using the information provided in the manual in order to check recent notifications of malfunctions Annual cleaning Clean the equipment in particular the heat sink and the ventilation openings on the REACT BATT Troubleshooting In order to understand and deal with warning Wxxx or error Exxx signals that appear on the system s display use t...

Page 150: ...ted slot If the signal persists also following the above checks contact customer assistance No code Waiting Sun Flashing green LED Waiting Sun The inverter goes into the Waiting Sun stage when following a W001 and or W002 warning the voltage from the photovoltaic generator is less than the activation voltage Vstart Check the input voltage on the inverter If it does not exceed Vstart check for the ...

Page 151: ... during the inverter s normal operation the grid frequency exceeds the minimum limit set by the operator Check the grid frequency in the inverter Check the grid frequency also on the supply If the voltage and the grid frequency come back within the limits also when the inverter is connected to the grid contact customer assistance W009 Empty Table Yellow LED Characterisation board for the wind gene...

Page 152: ...wer limitation code is active and on the basis of that carry out the necessary checks that might relate to various factors including settings by the user high grid frequency high grid voltage anti islanding low grid voltage high internal temperature high input voltage W022 Reactive power mode changed No LED not visualised on display Variation in means of managing reactive power Variation in the me...

Page 153: ...lly If the problem persists once the inverter has been switched off and back on again contact customer assistance W040 Batt 2 F1 No LED Error inside battery unit 2 Problem inside battery unit This condition can be transitory with automatic reset at the end of the alarm situation Error inside the inverter and cannot be checked externally If the problem persists once the inverter has been switched o...

Page 154: ...wise it is necessary to have good energy production and low absorption of domestic loads to carry out the recharging of the battery charge in DC W056 Power Engage Yellow LED CHECK BATT CABLE is displayed in the general information cyclical screens Problem with battery pack power connection cables Error detected on the power cables between the inverter unit and the battery unit Check the power line...

Page 155: ... 155 000570BG 8 Maintenance Скачано с сайта интернет магазина https axiomplus com ua ...

Page 156: ...n the inverter is configured with parallel inputs In this particular configuration the inverter checks the input voltage of each of the two channels and if the two voltages differ by more than 20Vdc the alarm is raised Check that the setting of the IN MODE switch is specifically set to PAR and that the jumpers between the two input channels have been included If the configuration of the inverter i...

Page 157: ...nd cannot be checked externally By its nature the alarm only occurs prior to connection to the grid If the problem persists once the inverter has been switched off and back on again contact customer assistance E021 Self Test Error 2 Yellow LED Failure of the test on the inverter s relay DC AC circuit Before connecting to the grid the inverter carries out some internal tests One of these tests conc...

Page 158: ...and back on again contact customer assistance E029 Mid Bulk OV Yellow LED Internal overvoltage on the measurement of the Mid bulk Error inside the inverter only triphase models Error inside the inverter and cannot be checked externally If the problem persists once the inverter has been switched off and back on again contact customer assistance E030 Error Meas Ileak Yellow LED High leakage current ...

Page 159: ... back on again contact customer assistance E049 AC FF Error Yellow LED Error in the AC feed forward circuit Error inside the inverter Error inside the inverter and cannot be checked externally If the problem persists once the inverter has been switched off and back on again contact customer assistance E050 AFDD Activated Yellow LED Arc Fault protection activated Possible photovoltaic arc detected ...

Page 160: ...rrent of battery charger Charger circuit Error inside the inverter Error inside the inverter and cannot be checked externally If the problem persists once the inverter has been switched off and back on again contact customer assistance E069 Charger SlowRamp Yellow LED Error internal to inverter linked to the battery pack charger circuit Charger circuit Error inside the inverter and cannot be check...

Page 161: ...er and contact customer assistance E084 BackFeed OC Yellow LED Return current to photovoltaic field The error occurs if the input voltage is particularly low typically in the evening in conditions of low irradiation and indicates a return current from the inverter to the photovoltaic panels If the error occurs in the evening or in conditions of low irradiation it must not be considered a problem b...

Page 162: ...r Check the limitation value set in Settings Service Power OF Derating LIMxxx CODE 02 Power limitation due to over voltage The message indicates that the user has set a power limitation due to overvoltage parameter U 10 min in order to reduce the maximum output power of the inverter when the reading of the average grid voltage exceeds certain limits The sampling of readings is done every 10 minute...

Page 163: ... for the inverter to cool down If the problem persists once the ambient temperature has returned to within the range contact customer assistance LIMxxx CODE 06 Power limitation due to input overvoltage The message indicates that a power limitation is active since an input overvoltage DC has been recorded LIM xxx Power reduction percentage Examples LIM 100 no power limitation LIM 50 limitation to 5...

Page 164: ...teps for REACT system switch off before removing one of the parts making up the system Never open the system parts in the case of humidity 95 Always carefully seal all unused openings Even though the device is equipped with an anti condensation valve air with extremely high levels of humidity can lead to the creation of condensation inside the inverter As the inverter is almost completely insulate...

Page 165: ...ists of 4 figures indicating the week first 2 digits and the year of production last 2 digits Update Version This information is available only for some inver ter models and can be found on the display by accessing the menu INFORMATION Firmware Stage 2 Registration on https registration abbsolarinverters com Go online and access https registration abbsolarinverters com Set the desired language and...

Page 166: ...he email used during registra tion and the Password obtained at the end of Stage 2 Access the section dedicated to requesting the second level password Choose the inverter model from the drop down list and insert Update Ver Serial Number and Week of Production of the inverter which were obtained previously Stage 1 Скачано с сайта интернет магазина https axiomplus com ua ...

Page 167: ...he passwords will be shown in a new window and at the same time sent to the email address used for registration The second level password enables access to the service menu which allows the inverter s sensitive parameters to be changed Proceed to changing the aforementioned parameters only when requested by the grid operator or by customer assistance Скачано с сайта интернет магазина https axiompl...

Page 168: ...ess the SETTINGS menu by entering the first level password default 0000 2 Access the Service sub menu by entering the second level password The password to access the Service menu can be obtained by registering at the site https registration abbsolarinverters com Before accessing the site it will be necessary to locate the information utilized to compute the password Inverter model Serial number a...

Page 169: ...mensions of the photovoltaic generator Behaviour of a system without leakage Due to the capacitive effect of the PV generator during the first moments that the voltmeter is connected between one of the two poles and ground it will measure a voltage of about Voc 2 which will tend to stabilize to around 0V if there is no ground leakage as shown in the graph below The internal resistance of the voltm...

Page 170: ...round a voltage of 200V is measured This means that if the system is made up of 10 modules in series and each one supplies 50V the leakage can be located between the 4th and 5th PV module Va voltage measured between pole and 200V Vb voltage measured between pole and 300V In all measurements with the ground of the inverter is indicated V 200 V 300 V t 50 V 50 V 50 V 50 V Va 50 V 50 V 1 2 3 4 7 8 5 ...

Page 171: ... is less than 1Mohm the inverter does not connect to the grid due to a low insulation of photovoltaic generator respect to ground I MODELS with high frequency transformer If the measured insu lation resistance Riso in case of input poles floating respect to ground or QF 1 if the one of input poles is grounded is less than 0 2Mohm the inverter does not connect to the grid due to a low insulation of...

Page 172: ...cates that the product must not be disposed of with domestic waste at the end of its useful life This product must be delivered to the waste collection point of the local community for recycling For further information refer to the public body responsible for waste disposal in the country Inappropriate disposal of waste can have a negative impact on the environment and human health owing to potent...

Page 173: ... 173 000339AG Further information For more information on ABB solar products and services visit www abb com solarinverters Скачано с сайта интернет магазина https axiomplus com ua ...

Page 174: ...Contact us www abb com solarinverters Скачано с сайта интернет магазина https axiomplus com ua ...

Reviews: