HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2
COMPANY CONFIDENTIAL
Date released: 16-08-2018
Page
5
of
128
Workflow with pre-fabricated concrete foundation
Workflow with metal frame foundation
Workflow with custom foundation (footprint)
Construct foundation of the ABB Pole
Pole foundation constructed on site or mounted on concrete floor
Workflow with pre-fabricated concrete foundation
Cables between the Power Cabinets and the ACS Control Module
Cables between the Power Cabinets
About placement and connection
Move Power Cabinet to position
Move cabinet with a forklift truck
Install Power Cabinet onto the foundation
Connect Power Cabinet to foundation
Open the door of the Power Cabinet
Move the sliding plate of the guidance plates of the cabinet
Route cables through guidance plates
Move sliding plates of the guidance plates of the cabinet
Install border covers of the Power Cabinet
Install border covers of metal frame foundation
Install front cover plate on foundation
Connect AC power cable and GND wires Power Cabinets
Connect the GND wire of the AC power cable
Install lightning protection (optional)
Connect the GND wire to the ABB Pole
Connect the GND wire between the Power Cabinets
Connect the DC power cables Power Cabinets
Connect AC utility power, Interlock and CAN cables Power Cabinet
Route the cables to the terminal blocks
Connect the AC utility power cable
Connect the communication cable Power Cabinet
Route the cable to the terminal blocks