6.2. Customer Acceptance Form (CAF)
After the commissioning is completed, the owner / site operator will sign the Customer
Acceptance Form (CAF). In certain circumstances ABB will be represented by a project
engineer.
The CAF contains information about:
the project (number, location, charger type),
a checklist about the delivery,
the commissioning SAT checklist,
list of remaining items.
After the CAF has been signed, the customer support will be handled by the ABB Service
department.
If there are any remaining items, they can be noted on the CAF document, together with the
agreed solution and the expected date of completion.