HVC 450 kW E-Bus Charger Installation Guide
Revision: 1.2
COMPANY CONFIDENTIAL
Date released: 16-08-2018
Page
8
of
128
1.
Introduction
1.1. Preface
This guide describes the planning and physical installation of the HVC E-Bus Charger at its
location for the North American (NA) region.
The HVC 450 kW E-Bus Charger is a DC fast charger system for hybrid or electrical buses
that are compatible with the OPP Charging standard
1
. It is not permitted to use the HVC 450
kW E-Bus Charger to charge any other equipment, or to use the HVC 450 kW E-Bus Charger
for any other purposes.
The HVC 450 kW E-Bus Charger uses high-amperage electric currents. Therefore the
installation must be planned carefully, and must be done by certified personnel only (according
to local standards).
Before installing the HVC E-Bus Charger, read this Installation Guide carefully and
attentively. Follow the instructions in this Installation Guide. ABB is not responsible for
any damage that has been caused by not or incorrectly following and executing the
instruction described in this manual.
1.2. Intended document users
This document is intended to be used by:
Customers who purchased a HVC 450 kW E-Bus Charger, or are in the process of
ordering and want to know in more detail how it has to be installed.
Contractors who are responsible for site preparation and/or installation of the HVC 450
kW E-Bus Charger.
1.3. Signs
The following signs are used on the equipment and in this manual:
DANGER
Hazardous voltage
Identifies a hazard that could result in severe injury or death through
electrocution.
WARNING
Various
Identifies a hazard that could result in severe injury or death.
WARNING
Rotating parts
Identifies a hazard that could result in injury due to the presence of
rotating or moving parts.
1
More information on OPP Charge via