5.4.2
Prepare the foundation for the power cabinet (concrete)
1. Make and install your own prefabricated or poured concrete foundation on site.
For important dimensions, refer to section
Caution: Make sure that the top surface of the foundation is above the
ground level, to prevent intrusion of water.
2. Put the cable conduits into the cable entries of the foundation.
3. Mark the position of the holes (A) for the grommet plate on the foundation. For
the correct dimensions, refer to section
4. Drill the holes.
5. Put the cables through the cable conduits in the foundation. Apply the full cable
slack.
For the specification of the cable slack, refer to section
.
6. Fill the foundation with gravel or another substance to prevent that rodents go
into the cabinet.
5.4.3
Prepare a metal foundation for the power cabinet
Preliminary requirements
•
Drill with screw tap
•
Torque wrench
•
Metal frame. Refer to
section
.
If you have not included
the foundation in the
initial order, contact the
manufacturer to order the
foundation for your power
cabinet. Refer to section
.
Procedure
1. Mark the position of the holes (A) on
the floor. For the correct dimensions,
refer to section
2. Drill and thread the holes.
Caution: Do not make holes
in the metal foundation that
can compromise the structural
integrity.
3. Guide the cables to the grommet plate
(B).
4. Align the metal frame (C) with the
threaded holes.
5. Install the fasteners (D) with washers.
6. Tighten the fasteners to the correct
torque. For the specification, refer to
section
C
B
D
A
Pre-installation
HVC 200/300/360-EN | 002
37