7.3
Deep battery test
The battery test takes approx. 3 minutes and should be performed only if:
•
There are no alarm conditions
•
The battery is fully charged
•
Mains is present.
The battery testing can be carried out independently of the operation mode (OFF-LINE or ON-LINE)
and whether or not the load is connected. The battery test procedure can be performed from the UPS
display, in the service setup mode.
7.4
Battery maintenance, disposal and recycling
The battery maintenance shall be done by a certified
Service Partner.
To ensure an optimum operation of the UPS system and
a continuous and efficient protection of the connected
load it is recommended to check the batteries every 12
months.
Batteries contain dangerous substances that will harm
the environment if thrown away. If you change the
batteries yourself, call qualified organizations for battery
disposal and recycling.
Summary of Contents for Conceptpower DPA 500
Page 1: ... Copyright 2017 ABB All rights reserved Operating manual Conceptpower DPA 500 100 500 kW ...
Page 2: ......
Page 79: ... Copyright 2017 ABB All rights reserved Appendix A Xtra VFI 3 ph UPS products ...
Page 88: ...Modifications reserved Page 88 94 Attachments Technical data sheet ...
Page 90: ......
Page 91: ... Copyright 2017 ABB All rights reserved Technical data sheet Conceptpower DPA 500 100 500 kW ...