![ABB AKD-10 Installation And Maintenance Manual Download Page 50](http://html.mh-extra.com/html/abb/akd-10/akd-10_installation-and-maintenance-manual_2063050.webp)
Cluster Components - 4000A & 5000A
Figure 47
Using proper safety procedures and wearing required Personal Protective Equipment
(PPE), remove breaker from compartment, and place it on a solid work surface in a welllit
location.
To uninstall the primary disconnects, remove the Adjusting nut from one of the long
bolts holding the primary disconnect assembly together
Carefully slide out the bolt while removing the flat washer, spring, upper retainer, bowtie
spacers, lower retainer, and fingers from the bottom of the assembly.
Do the same for the other assembly bolt and components.
Slide off the retainer clips.
Take off the main retainer from the stud.
Slide the main retainer over the stud.
Set a pair of bow-tie spacers into a pair of fingers, place a pressure plate retainer over
the spacers to hold them in position, and then turn the subassembly over. Hook them
into the main retainer.
Slide a long bolt through the hole in the retainer, between the finger, and then through
the clip and stud spacer.
Hold the bottom finger subassembly in place.
Place two fingers around the bolt from the top, hooking the fingers into the main
retainer. Then place a bow-tie spacer in each finger and hold them in position with a
pressure plate retainer.
Place a spring, bushing, and flat washer over the bolt, then secure with the Adjusting
nut.
Repeat Steps 7 through 13 for each set of fingers.
Adjust the nut to get a spacing of 0.865-0.895 inch for WPS-32/WPH-32/WPX-32/ WPS-
40/ WPX-40 with Double springs and 0.766—0.797 inch for WPS-50/WPX-50 between
the top of the upper retainer and the bottom of the flat washer.
Clean finger assemblies, if necessary, with a clean, lint-free rag and isopropyl alcohol or
acetone.
Be sure to apply a thin film of Mobilgrease 28 (DS50HD38) to the contact areas which slide
onto the switchgear stabs (See Figure 48/49, Step 2). This product is available in a 1-0z
tube, ABB Part #193A1751P1.
Figure 48 (WPS-32/WPH-32/WPX-32), Figure 49(WPS-40/ WPX-40) and figure 50 (WPS-
50/WPX-50) summarizes the steps for working with the primary contacts
C
Summary of Contents for AKD-10
Page 36: ...11 14 22 21 31 34 42 41 C2 C1 51 54 62 61 71 74 82 81 91 94 02 01 45 48 R1 R2 C ...
Page 38: ...C ...
Page 43: ...NOTES 1 WP WavePro fixed connection point C ...
Page 51: ...ONLY for 3200A Figure 48 Steps in Exploded Views for 3200A WPS 32 WPH 32 WPX 32 C ...
Page 52: ...ONLY for 3200A Figure 49 Steps in Exploded Views for 4000A WPS 40 WPX 40 C ...
Page 53: ...Figure 50 Steps in Exploded Views for 5000A WPS 50 WPX 50 ONLY for 3200A C ...
Page 65: ...Figure 64 Wiring of WP 4000A breaker with FAN control unit C ...
Page 74: ...Figure 75 Figure 76 WPF 16 with special 2500A Fuse WPF 16 2500A Fuse Tang Positions 74 C ...