8.  Troubleshooting

1) Main screen of the “Elios4you” App never shows power produced by the photovoltaic system

 

9

Turn the production CTs (white label) about face, so that the green dot or the arrow on the inside of the CT is positioned on the 
opposite side to that currently in use. 

 

9

Check that the cores of the CTs do not show any signs of internal damage.

2) Power level displayed by the App is much lower than that read by the inverter

 

9

Check that the grid CTs (yellow label) are positioned around the entire bundle of phases coming from the meter as in the diagram 
(see fig. 2); it is possible that the CTs may have been placed on a branch circuit. 

 

9

Check that one or more CTs do not show any clear signs of damage internally. 

3) Consumption detected and power produced follow the same curve

 

9

Check that the grid CT (yellow label) is positioned around the entire bundle of phases coming from the power company meter as in 
the diagram; in all probability, only the cable carrying consumption data is being detected.

 

9

Check that only the phase conductor of the system passes through the two CTs: if both phase and neutral pass through, an error 
will be induced.

 

9

Check that the two CTs do not show any clear signs of damage internally.

4) Power usage by the consumer appears to be detected in the grid icon

 

9

Check that the grid CTs (yellow label) are positioned on the lines leaving the relative meter, upstream of any branch made within 
the electrical system. 

5) There is never any indication on my system of power being supplied to the grid

 

9

Check that the grid CTs (yellow label) are positioned on the lines leaving the relative meter, upstream of any branch made within 
the electrical system.

6) At night there is zero usage, whereas during the day consumption is always higher than normal

 

9

Check that the grid CTs (yellow label) are positioned on the lines leaving the relative meter, upstream of any branch made within 
the electrical system. 

 

9

Check for correct correspondence between the sequence of supply voltages connected to the main switch and the sequence in 
which the CTs are positioned on the various conductors. 

7) App shows very high levels of consumption, whereas usage by the consumer is minimal

 

9

Check that the grid CTs (yellow label) are positioned on the lines leaving the relative meter, upstream of any branch made within 
the electrical system. 

 

9

Turn the grid CTs (yellow label) about face, so that the green dot or the arrow on the inside of the CTs is positioned on the opposite 
side to that currently in use.

9.  Conformity

All models comply with Directives 2014/30/UE(EMC), 2014/35/UE (LVD) e 2014/53/UE (RED). The appliance (or product) is subject to sorted 
collection, in compliance with local regulations on waste disposal currently in force. The Astrel Group hereby declares that this product is 
in compliance with essential requirements and other pertinent provisions established under Directive 2014/53/UE (RED). The declaration of 
conformity can be viewed at www.astrelgroup.com.

10.  Safety and disposal

Electrical and electronic equipment requiring sorted collection, in compliance with local regulations on waste disposal currently in force.

Astrel Group reserves the right to change product specifications without notice.

5.  Operation of button (table 2)

Function

Command

Meaning

First 
configuration

Press briefly
(6 second 
approx)

Procedure required by the “Elios4you” App when the device is first configured.
For more information: www.4-noks.com/tutorial

Reset

Press and 
hold (30 
seconds 
approx)

The Reset function restores the parameters of the device to the factory settings

6.  Meaning of Elios4you Pro terminal numbers (table 3)

Terminal

Meaning

1

SIG + (CT L1 Production – white ), red wire

2

SIG - (CT L1 Production – white ), black wire

3

SIG + (CT L2 Production – white ), red wire

4

SIG - (CT L2 Production – white ), black wire

5

SIG + (CT L3 Production – white ), red wire

6

SIG - (CT L3 Production – white ), black wire

7

SIG + (CT L1 Grid – yellow), red wire

8

SIG - (CT L1 Grid – yellow), black wire

9

SIG + (CT L2 Grid – yellow), red wire

10

SIG - (CT L2 Grid – yellow), black wire

11

SIG + (CT L3 Grid – yellow), red wire

12

SIG - (CT L3 Grid – yellow), black wire

7.  Technical specifications

General specifications

Control system for three-phase photovoltaic systems with Wi-Fi connection and App for smartphone/
tablet.  Maximum measurable power 15 kW, 50 kW or 100 kW (depending on model)

Power supply

400 V (3x 230 Vac + neutral) ± 10% 1.8  W

Radio specifications

•  Wi-Fi 802.11b/g/n
•  Access point (AP) Station (STA), B,G,N or mixed mode

Memory

Data log up to two months, in the event of no connection to tablet, with sampling every 15 minutes

Status displays

6 x Led

Connections

Screw terminals for power connections, measurement CTs, alarm inputs and control outputs

Current measurement

With split core CT (internal Ø 15 mm max)

Antenna

External antenna on SMA RP screw connector for data transmission via Wi-Fi

Outputs

•  Relay output (max 10 A @ 230 Vac)
•  Control output 0-10 Vdc

Inputs

2 x voltage-free alarm contact (N.O.)

Ambient parameters

•  Operating conditions: 0 to +50°C; <80% R.H., non-condensing
•  Storage conditions: -20 to +70°C; <80% R.H., non-condensing

Summary of Contents for ELIOS4YOU Pro

Page 1: ...Installation and instruction manual 4 noks Elios4you Pro IT EN FR DE...

Page 2: ...ption 12 Contents of the pack 12 Products compatible with Elios4you Pro 12 2 Safety warnings 12 3 Installation 12 Prior to installation 12 Warnings for installation 12 Fixing and first power up 12 Che...

Page 3: ...solution des probl mes 21 9 Conformit 21 10 S curit et limination 21 11 Sch ma d installation fig 3 22 Installations und Bedienungsanleitung 24 1 Allgemeine Beschreibung 24 Verpackungsinhalt 24 Mit El...

Page 4: ...mente raggiungibile 9 9 deve essere chiaramente indicato come componente per la disconnessione dell apparecchiatura L installatore deve provvedere alla protezione da sovraccarico del rel se utilizzato...

Page 5: ...bile che i TA siano stati posizionati in una diramazione dell impianto 9 9 Assicurarsi che uno o pi TA non riportino internamente segni evidenti di rotture 3 Il consumo rilevato segue l andamento dell...

Page 6: ...generico opzionale max 10 A 240 Vac Ingresso allarme 1 COMUNE allarme 1 Ingresso allarme 2 COMUNE allarme 2 Non cablare Non cablare Interruttore generale TA produzione etichetta bianca Punto verde e d...

Page 7: ...he installer and must meet certain requirements namely 9 9 it must be located in an easily accessible place 9 9 it must be clearly identified as a component used to disconnect the device The installer...

Page 8: ...the grid CTs yellow label about face so that the green dot or the arrow on the inside of the CTs is positioned on the opposite side to that currently in use 9 Conformity All models comply with Directi...

Page 9: ...3 N L1L2 L3 N L1 L2 L3 N Generic load optional 10 A max 240 Vac Production CT white label Green dot and direction of arrow K L toward main switch Relay contact N O X X X X X X X X IN 10 V GND Ctrl Ter...

Page 10: ...us les branchements mat riels doivent tre effectu s par du per sonnel qualifi et conscient des risques d une installation en tenant compte des normes minimales de s curit et en l absence de tension L...

Page 11: ...tr s peu 9 9 Contr lez que les TI de r seau tiquette jaune couvrent l ensemble des lignes la sortie du compteur avant leur ramification sur l installation lectrique 9 9 Faites pivoter les TI d change...

Page 12: ...L1 L2 L3 N Charge g n rique en option max 10 A 240 Vac TI production tiquette blanche Point vert et direction de la fl che K L vers l interrupteur g n ral Contact relais N O X X X X X X X X IN 10 V G...

Page 13: ...hl sse sind durch Fachpersonal ohne an liegende Spannung unter Ber cksichtigung der Installationsrisiken sowie der Mindestsicherheitsanforderungen auszuf hren F r die Erreichung der f r die einzelnen...

Page 14: ...gewissern Sie sich dass die Netz Stromwandler gelbes Etikett auf den Ausgangsleitungen des Z hlers vor einer Abzweigung der elektrischen Anlage gelegt sind 9 9 Die Austausch Stromwandler gelbes Etiket...

Page 15: ...max 10 A 240 Vac TA Erzeugung wei es Etikett Gr ner Punkt und Richtung des Pfeils K L zum Hauptschalter Relaiskontakt Schlie er X X X X X X X X IN 10 V GND Ctrl Klemmen N L1 L2 L3 Mindestquerschnitt...

Page 16: ...30 Note Notes Notes Anmerkungen...

Page 17: ...4 NOKS is a brand of ASTREL GROUP ASTREL GROUP SRL Via Isonzo 21 E 34070 Mossa GO Italy www astrelgroup com www 4 noks com 05T408110R4 0 Elios4you Pro Instruction manual IT EN FR DE 2018 06 29...

Reviews: